What is a Sprint Burndown Chart?
A Sprint Burndown Chart is a visual representation that displays the progress of a sprint in a Scrum project. It's a tool used to visualize the amount of work remaining in a sprint versus the amount of time left in the sprint.

Why is it Important?
A Sprint Burndown Chart is important because it helps the team to manage and track the progress of the work. It facilitates prediction of the sprint outcome, detects problems early, and fosters transparency, enabling the team to make necessary adjustments to meet the sprint goal.

How it Works?
A Sprint Burndown Chart works by plotting the remaining effort against time. The vertical axis represents the work remaining, while the horizontal axis represents time. As tasks are completed, the chart 'burns down,' reaching zero at the end of the sprint.

Exam Tips: Answering Questions on Sprint Burndown Chart
Understand the Basics: Much of the questioning might revolve around the basic concept, so you must understand what a Sprint Burndown Chart is and its fundamental purpose.
Interpretation Skills: Be able to interpret a given burndown chart successfully; understand what the various parts of the chart mean.
Application Knowledge: Know when and why a team should use a Sprint Burndown Chart. Understanding its benefits and implications is vital.
Problem-Solving: Some questions might present a problematic burndown chart and ask for a solution or improvement. Here, your analytical and problem-solving skills play a key role.

Go Premium

Professional Scrum Master I Preparation Package (2024)

  • 3547 Superior-grade Professional Scrum Master I practice questions.
  • Accelerated Mastery: Deep dive into critical topics to fast-track your mastery.
  • Unlock Effortless PSM I preparation: 5 full exams.
  • 100% Satisfaction Guaranteed: Full refund with no questions if unsatisfied.
  • bonus: If you upgrade now you get upgraded access to all courses
Sprint Burndown Chart practice test

A Sprint burndown chart is a visual measurement tool that shows the completed work per day against the projected rate of completion for the current project iteration. It is a tool for the Scrum Team to visualize how quickly they are working through the customer's user stories, reflecting how much work is left to be done. The horizontal axis represents time, and the vertical axis represents cards (stories). All members have real-time access to what remains in the Sprint Backlog in terms of work.

Time: 5 minutes   Questions: 5

Test mode:

Practice more Sprint Burndown Chart questions

More Sprint Burndown Chart questions
28 questions (total)
Go Premium

Professional Scrum Master I Preparation Package (2024)

  • 3547 Superior-grade Professional Scrum Master I practice questions.
  • Accelerated Mastery: Deep dive into critical topics to fast-track your mastery.
  • Unlock Effortless PSM I preparation: 5 full exams.
  • 100% Satisfaction Guaranteed: Full refund with no questions if unsatisfied.
  • bonus: If you upgrade now you get upgraded access to all courses