Directing a Project Purpose
The Directing a Project Process in PRINCE2 7 serves as the essential governance mechanism that enables the Project Board to maintain overall control and make key decisions throughout the project lifecycle. This process runs from project initiation through to project closure, providing a framework for executive decision-making at strategic levels.
The primary purpose of Directing a Project is to enable the Project Board to be accountable for the project's success by making timely decisions while delegating day-to-day management responsibilities to the Project Manager. This creates an efficient governance structure where senior stakeholders can oversee the project at appropriate intervals rather than being involved in routine operational matters.
Key aspects of this purpose include authorizing project initiation, ensuring that adequate resources and funding are available, approving the Project Initiation Documentation, and sanctioning each stage before it commences. The Project Board also provides guidance and direction when the Project Manager escalates issues or when tolerances are forecast to be exceeded.
The process ensures that there is a clear line of authority and accountability. It establishes the mechanism for the Project Board to verify that the project remains justified throughout its duration by reviewing the Business Case at key decision points. This ongoing validation helps organizations avoid continuing with projects that no longer deliver expected benefits.
Additionally, Directing a Project facilitates communication between the project and corporate or programme management, ensuring alignment with broader organizational objectives. The Project Board acts as a link between the project and external stakeholders, championing the project within the organization.
The process also provides for orderly project closure, ensuring that lessons are captured, products are handed over appropriately, and recommendations for follow-on actions are made. This comprehensive governance approach helps deliver successful outcomes while maintaining appropriate oversight and control mechanisms.
Directing a Project Objectives
The Directing a Project process in PRINCE2 7 provides the Project Board with the mechanisms to oversee and control the project while maintaining appropriate governance throughout its lifecycle. This process runs from project initiation through to project closure and enables senior management to fulfill their responsibilities effectively.
The key objectives of Directing a Project include:
1. **Authorization and Decision Making**: The Project Board must authorize key project stages, including initiation, subsequent stages, and project closure. They make critical go/no-go decisions at stage boundaries based on business justification.
2. **Governance and Oversight**: Ensuring the project remains viable and aligned with organizational strategy. The Board monitors progress through highlight reports and exception reports, intervening only when necessary to maintain management by exception principles.
3. **Guidance and Support**: Providing direction to the Project Manager when issues arise that exceed their delegated authority. This includes resolving escalated problems and making decisions on exception plans.
4. **Stakeholder Communication**: The Board represents the project externally, communicating with corporate management and key stakeholders about project status and outcomes.
5. **Resource Commitment**: Ensuring adequate resources are available for the project and authorizing their allocation at each stage.
6. **Business Case Viability**: Continuously monitoring whether the project remains justified from a business perspective. If viability becomes questionable, the Board has authority to prematurely close the project.
7. **Ad-hoc Direction**: Responding to requests for advice from the Project Manager throughout the project lifecycle.
The process consists of five activities: authorizing initiation, authorizing the project, authorizing a stage or exception plan, giving ad-hoc direction, and authorizing project closure. These activities ensure that senior management maintains control while allowing the Project Manager sufficient autonomy to manage day-to-day operations effectively within agreed tolerances.
Directing a Project Context
The Directing a Project process in PRINCE2 7 provides the Project Board with essential mechanisms to maintain overall control and make key decisions throughout the project lifecycle. This process operates at the strategic level, enabling senior management to govern the project through exception-based management rather than day-to-day involvement.
The context of Directing a Project encompasses several critical aspects. First, it establishes the framework through which the Project Board exercises its authority and accountability. The board members, including the Executive, Senior User, and Senior Supplier, use this process to provide direction, authorize work, and ensure the project remains viable and aligned with business objectives.
The process spans the entire project, from initiation through to closure. It begins when the mandate is received and continues until the project is formally closed. During this time, the Project Board makes decisions at key points, particularly at stage boundaries where they authorize progression to subsequent stages.
Key activities within this context include authorizing initiation, authorizing the project itself, authorizing stage or exception plans, providing ad-hoc direction when needed, and authorizing project closure. The board also confirms ongoing business justification by reviewing the Business Case at each decision point.
The Directing a Project process ensures that corporate or programme management receives appropriate visibility into project progress. It maintains communication channels upward to stakeholders and ensures governance requirements are met. The process also handles situations where tolerances are forecast to be exceeded, requiring the board to make decisions on exception reports.
Effective direction requires the Project Board to remain engaged yet efficient, making timely decisions based on information provided by the Project Manager. This balanced approach allows projects to proceed smoothly while maintaining appropriate oversight and control at the executive level.
Authorize Initiation
Authorize Initiation is a critical activity within the Directing a Project process in PRINCE2 7. This activity is performed by the Project Board and represents one of the first formal decision points in a PRINCE2 project. The purpose of Authorize Initiation is for the Project Board to decide whether to commit resources and time to properly plan and define the project before major investment begins.
When a Project Brief and outline Business Case have been prepared during the Starting up a Project process, these documents are presented to the Project Board for review. The Board must assess whether the project concept is viable, aligns with organizational strategy, and warrants further investigation through a detailed initiation stage.
During this authorization, the Project Board reviews several key elements including the Project Brief, the outline Business Case, the Stage Plan for the initiation stage, and the Project Product Description. They evaluate whether sufficient justification exists to proceed and whether the proposed approach is reasonable.
The Project Board has three possible decisions: approve initiation and allow the project to proceed into the initiation stage, request changes or additional information before making a decision, or reject the project entirely if it lacks sufficient merit or alignment with corporate objectives.
If approved, the Project Manager receives formal authorization to execute the initiation stage, which involves creating the detailed Project Initiation Documentation. This staged approach ensures that organizations do not commit significant resources to projects that have not been properly examined and justified.
Authorize Initiation demonstrates the PRINCE2 principle of continued business justification, ensuring that projects only proceed when there is adequate reason to invest further. It also supports management by stages by establishing a clear decision point before substantial work commences, giving the Project Board appropriate control over project investments from the earliest opportunity.
Authorize the Project
Authorize the Project is a critical activity within the Directing a Project process in PRINCE2 7. This activity represents the point where the Project Board makes a formal decision to commit resources and proceed with the project based on the Project Initiation Documentation (PID). The Project Board reviews the PID, which contains comprehensive information about the project including the Business Case, Project Plan, management approaches, and control mechanisms. This documentation provides the board with everything needed to make an informed decision about project viability. During this authorization, the Project Board assesses whether the project remains justified from a business perspective. They evaluate the benefits, costs, risks, and timescales to determine if the investment is worthwhile. The board also confirms that adequate controls are in place and that the project aligns with organizational strategy. The Project Board has three possible decisions: approve the project and authorize the first stage, request changes to the PID before approval, or reject the project if it no longer appears viable. If approved, the board grants permission for the Project Manager to proceed with delivery. Key considerations during authorization include confirming the Business Case is sound, ensuring risks are acceptable, verifying that the project team has sufficient capability, and checking that stakeholder engagement strategies are appropriate. The board must be satisfied that governance arrangements will enable effective oversight throughout the project lifecycle. This authorization establishes the baseline against which project performance will be measured. It also confirms the tolerances within which the Project Manager can operate before needing to escalate issues to the board. By formally authorizing the project, the Project Board accepts accountability for its success and commits to providing ongoing direction and support throughout the project duration.
Authorize Stage or Exception Plan
Authorize Stage or Exception Plan is a critical activity within the Directing a Project Process in PRINCE2 7. This activity empowers the Project Board to make informed decisions about whether the project should proceed to its next stage or follow an exception plan when tolerances have been exceeded.
When a Stage Boundary is reached, the Project Manager prepares an End Stage Report and a Stage Plan for the upcoming stage. The Project Board then reviews these documents to assess project performance and viability before authorizing continuation. This review ensures that the business case remains valid, risks are acceptable, and the project continues to align with organizational objectives.
The authorization process involves the Project Board evaluating several key elements: the current stage performance against planned targets, updated business case viability, risk exposure and mitigation strategies, resource availability for the next stage, and any lessons learned that should influence future work. The Board must be satisfied that continuing the project represents good value and remains strategically important.
When an Exception Plan is submitted, it indicates that stage or project tolerances have been breached or are forecast to be breached. The Exception Plan replaces the remaining portion of the current Stage Plan and requires Project Board approval before implementation. This mechanism ensures that significant deviations from agreed parameters receive appropriate executive attention and decision-making.
The Project Board has several options when reviewing these plans: they may approve the plan as submitted, request modifications, put the project on hold pending further information, or recommend project closure if continuation is no longer justified. This decision-making authority represents a key governance control within PRINCE2, ensuring that management by exception operates effectively while maintaining appropriate oversight of project investments and strategic alignment throughout the project lifecycle.
Give Ad Hoc Direction
Give Ad Hoc Direction is a key activity within the Directing a Project Process in PRINCE2 7. This activity enables the Project Board to provide guidance, make decisions, and respond to situations that arise between formal stage boundaries or scheduled reporting periods.
The Project Board members are typically senior executives with other responsibilities, so they cannot be involved in day-to-day project management. However, projects rarely progress exactly as planned, and situations emerge that require board-level input or decisions. Give Ad Hoc Direction addresses this need by establishing a mechanism for ongoing governance throughout the project lifecycle.
This activity covers several important functions. First, it allows the Project Board to respond to exception reports when the project manager identifies that tolerances may be exceeded. The board can then decide whether to approve an exception plan, request changes, or take other corrective action.
Second, the board provides informal advice and guidance when the project manager needs clarification on strategic matters, stakeholder concerns, or organizational priorities. This ensures alignment between the project and broader business objectives.
Third, Give Ad Hoc Direction enables the board to make decisions on escalated issues or risks that fall outside the project manager's authority. This maintains appropriate governance while keeping the project moving forward.
Fourth, the board can respond to external changes affecting the project, such as shifts in business strategy, market conditions, or regulatory requirements.
The activity emphasizes management by exception, meaning the board intervenes only when necessary rather than micromanaging. This approach respects both the project manager's authority and the board members' limited availability.
Effective ad hoc direction requires clear communication channels between the project manager and board members, well-defined escalation procedures, and mutual understanding of decision-making authorities. This ensures timely responses to emerging situations while maintaining proper project governance.
Authorize Project Closure
Authorize Project Closure is a critical activity within the Directing a Project process in PRINCE2 7. This activity is performed by the Project Board and represents the formal conclusion of a project's lifecycle. The Project Board must make an informed decision about whether the project can be officially closed based on the information provided by the Project Manager in the End Project Report and Lessons Report.
When authorizing project closure, the Project Board reviews several key elements. They assess whether the project has delivered its intended products and whether these products have been accepted by the appropriate parties. The Board examines if all planned handover activities have been completed and if the products have been successfully transferred to operational use or the relevant stakeholders.
The Project Board also verifies that appropriate follow-on action recommendations have been documented for any work that falls outside the project's scope but may require future attention. They ensure that lessons learned throughout the project have been captured and will be made available for future projects within the organization.
Additionally, the Board confirms that benefits achieved during the project have been documented and that arrangements are in place for measuring benefits that will be realized after the project closes. They review whether all project resources have been released or have plans for release.
The authorization can result in three possible outcomes: the project is approved for closure, the project requires additional work before closure can be granted, or in exceptional circumstances, the project may need to continue if critical elements remain incomplete.
Once authorized, the Project Board notifies corporate or programme management of the project's closure, ensuring organizational governance requirements are satisfied. This formal authorization provides a clear end point for the project, releases resources, and ensures accountability is properly transferred to those responsible for ongoing operations and benefits realization.