You are managing a project for an oil extraction facility. During the initial stages, a team member visualizes and maps out different environmental and technical scenarios ranging from optimal to adverse outcomes. What risk identification technique is being applied?
a.
A comprehensive root cause analysis combined with expert judgment and documentation review
b.
Scenario Analysis
c.
Historical data assessment using advanced predictive modeling algorithms
d.
Facilitated risk assessment matrix evaluation with stakeholders
Intermediate