According to PRINCE2, which of the following correctly describes the minimum required composition of the Project Board?
a.
Senior User, Project Support, and Team Manager
b.
Executive, Project Manager, and Change Authority
c.
Project Manager, Team Manager, and Project Assurance
d.
Executive, Senior User, and Senior Supplier