According to PRINCE2, what is the PRIMARY method through which the Project Board gives direction to the Project Manager?
a.
Through formal authorizations at decision points
b.
Through a continuous approval process that spans all management activities
c.
Through daily meetings and hands-on management of project activities
d.
Through constant review of all project documentation and amendment of plans