Critical Path Method
Technique to schedule project activities
The Critical Path Method (CPM) is a project management technique used to schedule project activities. It identifies the longest stretch of dependent tasks in a project from start to finish, determining the minimum time needed to complete the project. CPM involves several key elements: 1. Activity…
CAPM - Critical Path Method Example Questions
Test your knowledge of Critical Path Method
Question 1
While managing a project, you realise that Task E of 10 days and Task F of 5 days can be undertaken concurrently after finishing Task D of 7 days. What is the fastest duration to complete Tasks D, E and F according to the network diagram?
Question 2
You are managing a construction project to build a house. The foundation needs one week to be settled before the walls can be erected. Due to an upcoming storm, you need to finish the construction soon. As a project manager, what should be your strategy?
Question 3
In a software project, tasks A, B, C and D are sequenced in order. Each task takes 5 days to complete. The entire project has a deadline of 25 days. If task C has been finished on the 15th day, when do you expect to start task D?