PMI-ACP - Lean Software Development
Master
1/100
Your Agile team has to make a decision on adopting a new project strategy. However, the long-term implications and values are still unclear. How do you align this scenario with deciding as late as possible Agile principle?
a.
Let the team vote to decide on adopting the new strategy.
b.
Carry on with the current strategy until more information about the implications of the new strategy becomes clear.
c.
Avoid making a decision and continue in the current direction.
d.
Immediately adopt the new strategy without understanding its implications.