You are in the Close Procurement process of a project. The procurement audit displayed non-compliance issues with the vendor. What should be your next step in dealing with this situation?
a.
Ignore the audit findings as the project is at the closing stage
b.
Suppress the audit findings to maintain good relations with the vendor
c.
Document the issues and discuss them with the vendor
d.
Leak the audit findings to the media