Directing a Project Process

Understand Project Board responsibilities throughout the project.

Covers the Directing a Project process which enables the Project Board to exercise overall control while delegating day-to-day management. Focuses on understanding the purpose, objectives, and context of authorizing initiation, authorizing the project, authorizing stage or exception plans, giving ad-hoc direction, and authorizing project closure.
5 minutes 5 Questions

The Directing a Project process in PRINCE2 7 is a critical process that runs throughout the entire project lifecycle and is owned by the Project Board. This process enables the Project Board to exercise overall control and make key decisions while delegating day-to-day management to the Project Man…

Concepts covered: Authorize the Project, Authorize Project Closure, Directing a Project Context, Authorize Initiation, Directing a Project Purpose, Directing a Project Objectives, Authorize Stage or Exception Plan, Give Ad Hoc Direction

Test mode:
PRINCE2 Foundation - Directing a Project Process Example Questions

Test your knowledge of Directing a Project Process

Question 1

A pharmaceutical company is executing a project to develop a new drug distribution platform. The project is currently in Stage 2 of 5. During a routine audit, the corporate compliance department identifies that recent regulatory changes in three key markets will require substantial modifications to the platform's data handling capabilities. The Project Manager estimates these changes will add 8 weeks to the current stage timeline and increase costs by 18%, which falls just within the stage tolerances approved by the Project Board. The Project Manager believes they can absorb these changes and still meet stage objectives. The Project Manager is preparing to implement the changes and will report the variance in the next highlight report. What should occur in this situation?

Question 2

A software development project has completed Stage 2 successfully. The project manager submits the End Stage Report showing all deliverables met acceptance criteria, costs were within tolerance, and the Stage 3 Plan requests authorization for the next four months of development work valued at £280,000. However, two project board members are unavailable for the next three weeks due to other business commitments, and one board member suggests the project manager should proceed with Stage 3 activities while waiting for formal authorization since the project is performing well. What should happen in this situation?

Question 3

Which management product must the Project Board review before they can make a decision regarding whether to authorize an Exception Plan?

More Directing a Project Process questions
231 questions (total)