Estimate at Completion (EAC)
Estimate at Completion (EAC) represents the forecasted value of costs at the end of the project. It provides an estimate of what the project is expected to cost. Normally, this estimate is a combination of the money already spent (actual costs) and the estimate to complete (the remaining work). This measure provides project managers and stakeholders with a tool to predict the total project cost based on current project performance and helps them to ascertain whether budget adjustments are necessary.
Guide on Estimate at Completion (EAC)
It is a prediction of the total cost of a project or a task at the end when all the work has been completed. It's a technique of earned value management, a project management technique for estimating how a project is performing.
Importance of Estimate at Completion (EAC):
EAC is important as it gives the project team a clear indication of the anticipated final cost of the project. This allows project managers and sponsors alike, to make informed decisions regarding the project and its budget. It also aids in analyzing the cost performance of the project and the efficiency of the cost management processes implemented.
How EAC works:
EAC is calculated using the formula: EAC = AC + ETC, where AC is the Actual Cost and ETC is the Estimate To Completion.
It's a forecast of future project cost performance based on both past performance and estimated future performance.
Answering Questions on EAC in an Exam:
To calculate EAC in an exam, you'll need the following: the actual costs of tasks completed (AC), the budgeted cost of work scheduled (BCWS), and the budgeted cost of work performed (BCWP). The formula to find the EAC = AC + [(BAC - EV) / CPI].
Exam Tips:
- Understand the concept and importance of EAC.
- Remember the formula of EAC = AC + ETC or EAC = AC + [(BAC - EV) / CPI] based on available data.
- Practice EAC calculations using a variety of data sets.
- Remember that EAC is primarily an estimation, and it may change as the project progresses.
CAPM - Estimate at Completion (EAC) Example Questions
Test your knowledge of Estimate at Completion (EAC)
Question 1
You're working on a project with a BAC of $120,000 and a CPI of 1. If the project progress continues at this performance, what would be the project's EAC?
Question 2
In a project where the BAC is $400,000, AC is $150,000, and EV is $120,000, which formula best represents the Estimate at Completion (EAC) assuming the current cost variance will persist?
Question 3
In a project where the Budget at Completion (BAC) is $600,000, the Actual Cost (AC) is $250,000, and the Earned Value (EV) is $200,000, which formula should be used to calculate the Estimate at Completion (EAC) if we assume future cost performance will improve?