Activity-Based Costing

5 minutes 5 Questions

Activity-Based Costing, often abbreviated as ABC, is a method used in project management to assign the direct costs of activities necessary for producing the specific goods and services. Unlike traditional costing methods, which assign costs to products based on an average overhead rate, ABC identi…

Test mode:
CAPM - Activity-Based Costing Example Questions

Test your knowledge of Activity-Based Costing

Question 1

As a project manager in a housebuilding project, you've realized that the activity 'Electrical Wiring Installation' isn't in line with calculated costs under activity-based costing. Considering indirect costs from the owner of the building's requirements, what's the best adjustment?

Question 2

As a project manager, you have implemented activity-based costing on your project. The project is delayed and over budget. Upon inspecting, you discovered that the activity 'Materials Procurement' is taking much longer and requiring more resources than anticipated. What is the probable cause?

Question 3

You are handling a construction project. You realize that cost estimations are exceeding mainly due to miscalculation in the cost of laying the foundation. What would be an appropriate solution in this situation if you were implementing activity-based costing?

More Activity-Based Costing questions
12 questions (total)