CM Fee Structures and General Conditions
In the Certified Construction Manager (CCM) body of knowledge, Professional Practice covers how a construction manager (CM) is compensated and how project overhead is defined through fee structures and general conditions. CM Fee Structures: The CM's fee is the compensation for professional services, distinct from the cost of the work itself. Common structures include: (1) Lump Sum/Fixed Fee – a set amount for a defined scope, offering owner cost certainty but requiring clear scope definition; (2) Percentage of Construction Cost – fee calculated as a percentage of the total construction value, simple but potentially creating a disincentive to control costs; (3) Cost Plus Fixed Fee – reimbursement of actual costs plus a predetermined fee, often used in CM at-Risk; (4) Hourly or Time-and-Materials – billed at agreed rates, suitable for undefined or pre-construction services; and (5) Guaranteed Maximum Price (GMP) with Fee – the CM commits to a cost ceiling, with the fee covering profit and home-office overhead, sometimes with shared savings incentives. Fee selection depends on delivery method (CM Agency vs. CM at-Risk), risk allocation, scope certainty, and owner preference. General Conditions: These are the project-specific, field-related overhead costs required to support construction but not attributable to a single trade. Examples include project staff salaries (superintendent, project manager, engineers), temporary facilities (trailers, utilities, fencing, sanitation), safety programs, hoisting and equipment, cleanup, insurance, bonds, permits, and site security. General conditions may be priced as a lump sum, a percentage, or a reimbursable cost with a not-to-exceed limit, and typically appear as a separate line item in the budget or GMP. Professionally, the CCM must clearly separate fee (profit and corporate overhead) from general conditions (direct field support costs) in contracts to ensure transparency, avoid double-counting, support auditability, and align incentives among owner, CM, and trade contractors. Clear definition protects the CM's ethical obligation to act in the owner's best interest.
CM Fee Structures and General Conditions: A Complete CCM Exam Guide (Professional Practice)
The Certified Construction Manager (CCM) exam, administered by the Construction Manager Certification Institute (CMCI) of CMAA, tests your ability to think like an owner's advocate. Within the Professional Practice domain, few topics reveal that mindset more directly than how a Construction Manager is paid and what the project's General Conditions are. Fee structure determines the CM's incentives, risk exposure, and relationship to the owner. General Conditions determine both the legal framework of the contract and a significant slice of the project budget. If you misunderstand either, you will misread scenario questions about CM-Agency versus CM-at-Risk, Guaranteed Maximum Price (GMP) development, change order pricing, and conflicts of interest.
Expect this material to appear in at least a handful of questions, often disguised inside scenario stems about delivery methods, cost control, or ethics. Mastering it also pays dividends in the Cost Management and Contract Administration domains, because fee and General Conditions concepts flow into budgeting, GMP reconciliation, and claims.
Part 1: What a CM Fee Structure Is
A CM fee structure is the contractual method by which the Construction Manager is compensated for professional services. The structure selected depends on the delivery method, the phase of the project, how well scope is defined, and how the owner wishes to allocate risk. The principal structures you must know are:
1. Lump Sum / Fixed Fee. A single, predetermined amount for a defined scope of services. The CM absorbs the risk of underestimating effort; the owner enjoys cost certainty. Best used when scope, schedule, and staffing are well defined. Changes to scope or duration require fee adjustments through amendment.
2. Percentage of Construction Cost. The fee is a stated percentage of the estimated or actual construction cost. Simple to administer and common historically for design and CM services. Its weakness is the potential misalignment of interests: as construction cost rises, so does the fee. Many owners and most public agencies now avoid or cap this approach, and cost-plus-percentage-of-cost arrangements are prohibited on federal contracts.
3. Cost Plus Fixed Fee. The owner reimburses the CM's actual allowable costs (salaries, burden, expenses) plus a fixed fee representing profit and home-office overhead. The fee does not grow if costs grow, which removes the incentive to inflate cost while still protecting the CM from unknowns. Common for CM-at-Risk construction-phase services.
4. Hourly Rates / Time and Materials (T&M). The CM bills agreed hourly or monthly billing rates for each staff classification, often multiplied by a negotiated multiplier covering overhead and profit, plus reimbursable expenses. Frequently paired with a Not-to-Exceed (NTE) ceiling to protect the owner. This is the dominant structure for CM-Agency services, where the staffing plan drives the fee.
5. Staffing Plan Based Fee. A refinement of the hourly approach: the CM proposes a matrix of positions, durations, and rates for each phase. The sum becomes the fee, usually fixed or NTE. Owners like it because it is transparent and auditable; CMAA guidance emphasizes that the staffing plan should be tied to the project's scope of services.
6. GMP-Based Compensation (CM-at-Risk). Under CMAR, the CM typically receives a preconstruction fee (often lump sum or hourly) and a construction phase fee (fixed or a percentage of the Cost of the Work). The construction fee, General Conditions, Cost of the Work, and contingency are rolled into the GMP. The CM is at risk for costs exceeding the GMP. Savings below the GMP may revert entirely to the owner or be shared through a shared savings or incentive clause.
7. Incentive and Performance-Based Fees. Portions of the fee may be tied to schedule milestones, cost targets, safety records, or quality metrics. These align interests but require objective, measurable criteria to avoid disputes.
Part 2: What General Conditions Are
The term General Conditions is used in two distinct ways, and the exam expects you to recognize which meaning a question intends.
Meaning A: General Conditions of the Contract (a document). This is the portion of the contract documents that sets forth the rights, responsibilities, and relationships of the parties and the administrative procedures governing the work. Examples include AIA A201, ConsensusDocs 200 series, and EJCDC C-700. They address topics such as the owner's and contractor's duties, the role of the architect or CM, changes in the work, time, payments, insurance and bonds, claims, and termination. Supplementary Conditions modify the General Conditions for a specific project. Division 01 General Requirements in the specifications provide the procedural and administrative detail (submittals, temporary facilities, closeout) that implement the General Conditions.
Meaning B: General Conditions Costs (a budget category). These are the jobsite overhead costs of managing and supporting construction that are not attributable to any single work item. Typical General Conditions costs include: project management and supervisory staff (project manager, superintendent, project engineer, field office staff), field office trailers and furnishings, temporary utilities, temporary roads and fencing, hoisting and scaffolding when not in a trade scope, safety programs and equipment, site security, cleanup and dumpsters, small tools, permits, surveying and layout, quality control testing when assigned to the contractor, insurance and bonds (sometimes listed separately), and project-related travel. They are distinguished from home office overhead (executive salaries, corporate accounting, marketing, rent) which is recovered through the fee, not through General Conditions.
How General Conditions Costs Are Priced. In CMAR arrangements, General Conditions may be priced as a lump sum, as a monthly rate times duration, as a cost-reimbursable line with an NTE, or as a percentage of the Cost of the Work. Lump sum or monthly rate pricing gives the owner certainty and gives the CM an incentive to finish on time. Cost-reimbursable pricing is more transparent but exposes the owner to schedule extension costs. Because General Conditions are time-driven, they are a central element of delay claims: extended General Conditions are among the most common damages sought when the schedule is extended through no fault of the contractor.
Part 3: How It All Works Together
Consider the anatomy of a typical CM-at-Risk GMP:
GMP = Cost of the Work (subcontracts and self-performed work) + General Conditions + CM Contingency + CM Fee (overhead and profit).
Note the separation: the fee compensates the firm for home-office overhead and profit; General Conditions compensate for jobsite management costs; contingency covers unforeseen costs within the scope; and the Cost of the Work is the direct construction cost. Exam questions frequently test whether you can place a given cost in the correct bucket. A superintendent's salary is General Conditions, not fee. The president's salary is fee (home office overhead), not General Conditions. An unexpected subcontractor default cost may be drawn from contingency. A design error correction is typically an owner cost through change order, not a contingency draw, unless the contract says otherwise.
In CM-Agency, the CM is the owner's fiduciary advisor and does not hold trade contracts. The fee is usually hourly or staffing-plan based with an NTE, plus reimbursables. There is no CM contingency within a GMP because the CM carries no cost-of-work risk; the owner holds the contingency. General Conditions costs are carried by the trade contractors or by a separate general conditions contractor, and the CM reviews and manages them on the owner's behalf.
In CM-at-Risk, the CM converts from advisor to contractor at the GMP. The preconstruction fee ends; the construction fee, General Conditions, and contingency are fixed in the GMP amendment. The owner must scrutinize the General Conditions estimate during GMP negotiation, because inflated staffing or duration assumptions are a common place for hidden margin. CMAA practice encourages open-book, auditable General Conditions and a clear definition of what is reimbursable versus included in fee.
Interest Alignment and Ethics. The CMAA Code of Professional Ethics requires CMs to serve the owner's interests and to disclose any compensation arrangement that could create a conflict. A fee that increases with construction cost, or undisclosed markups on General Conditions, can be an ethical problem as well as a commercial one. When an exam question asks which fee structure best protects the owner or best aligns interests, the answer will usually favor fixed fee, NTE, or incentive structures over uncapped percentage structures.
Part 4: How to Answer Exam Questions on This Topic
Approach each question with a four-step analysis:
Step 1: Identify the delivery method and the CM's role. Is the CM an agent (no cost risk) or at risk (holds trade contracts, provides GMP)? This determines whether fee, contingency, and General Conditions behave as owner-controlled or CM-controlled items.
Step 2: Identify which meaning of General Conditions is in play. If the stem refers to a document, clauses, rights, or responsibilities, think AIA A201 or ConsensusDocs. If it refers to dollars, staffing, trailers, or duration, think jobsite overhead costs.
Step 3: Ask who bears the risk and who benefits. Lump sum shifts risk to the CM. Cost-reimbursable shifts risk to the owner. Percentage fees reward higher cost. Shared savings reward lower cost. Monthly General Conditions rates reward schedule performance.
Step 4: Apply the owner's-advocate lens. CMAA exam answers consistently favor transparency, documented staffing plans, defined scope, and alignment of CM and owner interests.
Exam Tips: Answering Questions on CM Fee Structures and General Conditions
Tip 1. Memorize the distinction between fee, General Conditions, contingency, and Cost of the Work. Nearly every GMP question hinges on placing a cost in the right category.
Tip 2. Home office overhead belongs in the fee; jobsite overhead belongs in General Conditions. If a question lists the project superintendent, field trailer, or temporary power, the answer is General Conditions.
Tip 3. When asked which fee type creates a potential conflict of interest, select percentage of construction cost or cost-plus-percentage. When asked which is prohibited on federal work, select cost-plus-percentage-of-cost.
Tip 4. When asked which fee structure is most appropriate for CM-Agency with an undefined or evolving scope, select hourly rates with a not-to-exceed limit based on a staffing plan.
Tip 5. When asked how to give the CM an incentive to finish early, look for a lump sum or monthly-rate General Conditions arrangement or a shared savings clause, not cost-reimbursable General Conditions.
Tip 6. Recognize that extended General Conditions are the typical measure of contractor delay damages for a compensable, owner-caused delay, while home office overhead is usually calculated separately (for example, by the Eichleay formula).
Tip 7. Supplementary Conditions modify the General Conditions document for a specific project; Division 01 General Requirements provide administrative procedures. Do not confuse these three terms.
Tip 8. In CMAR, the preconstruction fee and construction-phase fee are separate; the GMP is typically established by amendment when documents are sufficiently complete, and the fee percentage is usually applied to the Cost of the Work, not to itself.
Tip 9. Shared savings clauses: savings below the GMP are shared per an agreed ratio only if the contract provides for it; the default in many standard forms is that unspent GMP reverts to the owner. Read the stem for what the contract says.
Tip 10. Watch for ethics crossover. Undisclosed markups, fee arrangements contingent on construction cost growth, or accepting compensation from trade contractors violate the CMAA Code of Professional Ethics.
Tip 11. Eliminate answers that increase owner risk without a corresponding benefit. The CCM exam rewards the owner's-advocate perspective.
Tip 12. Practice reading long scenario stems quickly for key words: agency, at-risk, GMP, NTE, staffing plan, reimbursable, lump sum, percentage, contingency, extended, delay, Supplementary Conditions, Division 01. Each word points toward a specific concept and narrows the answer choices.
Quick Reference Summary
Fee structures: Lump Sum (CM risk, cost certainty); Percentage of Cost (simple, conflict risk); Cost Plus Fixed Fee (reimburse costs, fixed profit); Hourly/T&M with NTE (CM-Agency standard); Staffing Plan Based (transparent, auditable); GMP with Shared Savings (CMAR, incentive aligned); Performance Incentives (measurable targets).
General Conditions (document): AIA A201, ConsensusDocs 200, EJCDC C-700; modified by Supplementary Conditions; implemented by Division 01.
General Conditions (cost): jobsite overhead such as supervision, field office, temporary facilities, safety, cleanup; time-driven; priced lump sum, monthly, reimbursable NTE, or percentage; central to delay claims.
GMP anatomy: Cost of the Work + General Conditions + Contingency + Fee.
Master these relationships, apply the owner's-advocate lens, and questions on CM Fee Structures and General Conditions become among the most predictable points on the CCM exam.
CMAA CCM - CM Fee Structures and General Conditions Example Questions
Test your knowledge of CM Fee Structures and General Conditions
Question 1
Under a construction management at-risk agreement with a guaranteed maximum price, which components are typically included within the GMP?
Question 2
On a transit station, the owner holds a construction management at-risk agreement with a guaranteed maximum price. General conditions are a stipulated lump sum within the GMP, separate from the CM's fee, which is a percentage of the cost of the work. Midway through construction, the CM's field supervision and temporary facility costs are running ahead of that lump sum because the CM's own trade sequencing has taken longer than planned. The owner has issued no changes. Which interpretation of this overrun is correct?
Question 3
On a bridge replacement, the owner's agency construction manager is paid a fixed fee plus reimbursable costs. The agreement lists the reimbursables as the field office, site staff salaries, materials testing and job-site travel. It states that home-office services are paid within the fixed fee. A monthly invoice includes field office rent and hourly charges for a home-office scheduler who updates the project schedule. How should the owner's representative treat the invoice?