Lead Time
Lead Time in the Scrum context refers to the complete journey a piece of work undertakes from the time it enters the system until it is finished. This includes time during which work awaits prioritization, is in progress or under review. It is a vital performance metric as it helps the team underst…
CSM - Lead Time Example Questions
Test your knowledge of Lead Time
Question 1
A team observes that their Lead Time is increasing over time. Which of these actions should the team take?
Question 2
A project experiences long Lead Times, but short Cycle Times. Where should the team focus their improvement efforts?
Question 3
A project has a Lead Time of 30 days, and a Cycle Time of 10 days. A feature is requested with high urgency. Calculate the quickest delivery time.