Dependency Determination and Types in CPM
In the context of the Critical Path Method (CPM), defining and analyzing dependencies between project activities is a fundamental step in constructing an accurate project schedule. Dependencies dictate the sequence in which tasks are performed and influence the timing relationships between activities. Properly identifying and implementing dependencies ensures logical workflow and allows for effective management of project timelines. There are four primary types of activity dependencies: 1. **Finish-to-Start (FS)**: The successor activity cannot start until the predecessor activity has finished. This is the most common dependency type and represents a typical sequential relationship. For example, you cannot begin painting a wall (successor) until the wall has been constructed (predecessor). 2. **Start-to-Start (SS)**: The successor activity cannot start until the predecessor activity has started. This dependency is used when two activities can occur in parallel after both have begun. For instance, once design work starts, coding can commence, allowing for overlapping work. 3. **Finish-to-Finish (FF)**: The successor activity cannot finish until the predecessor activity has finished. This relationship is used when the completion of one task is contingent upon the completion of another. For example, editing a document cannot be completed until writing the document is finished. 4. **Start-to-Finish (SF)**: The successor activity cannot finish until the predecessor activity has started. This is the least common type and is used in scenarios where the successor must continue until the predecessor begins. An example might be a night shift guard (successor) cannot finish duty until the day shift guard (predecessor) arrives. Dependencies can also be categorized based on their nature: - **Mandatory Dependencies**: These are inherent in the nature of the work and are often contractually or physically required. They represent hard logic. For example, you must receive approval before you can proceed with procurement. - **Discretionary Dependencies**: Also known as soft logic, these are defined by project teams based on best practices or preferences. They offer flexibility in sequencing and can be adjusted to compress schedules if necessary. - **External Dependencies**: Dependencies that involve relationships between project activities and non-project activities, which are outside the project team's control. For example, waiting for government permits. Understanding and accurately modeling these dependencies is crucial for constructing the project’s schedule network diagram. It ensures activities are logically sequenced, resource allocations are optimized, and potential scheduling conflicts are minimized. Dependencies affect the calculation of early start (ES), early finish (EF), late start (LS), and late finish (LF) dates during the forward and backward pass techniques in CPM. Incorrect dependency determination can lead to flawed critical path identification, resulting in schedule delays, resource bottlenecks, and cost overruns. Effective dependency management enhances project control by providing clarity on task relationships, facilitating communication among stakeholders, and allowing for proactive risk management. It enables project managers to foresee the impact of changes in one activity on the rest of the schedule and adjust plans accordingly to maintain project objectives.
Dependency Determination and Types in Critical Path Method (CPM)
Dependency determination is a fundamental component of the Critical Path Method because it establishes the logical relationships between activities in a project schedule. These relationships determine the sequence of work and ultimately affect the critical path calculation. Without properly identified dependencies, a project schedule becomes unreliable, leading to:
• Unrealistic timelines
• Resource conflicts
• Inability to identify the critical path accurately
• Ineffective schedule compression attempts
• Poor project control and monitoring
What are Dependencies in CPM?
Dependencies in CPM represent the logical relationships between activities that determine the sequence in which project work must be performed. These relationships answer the question: "What activities must finish before others can start?"
A dependency consists of a predecessor activity (which comes first) and a successor activity (which follows). The relationship between these activities is defined by one of four dependency types.
The Four Types of Dependencies in CPM
1. Finish-to-Start (FS) - The most common dependency type where a successor activity cannot start until its predecessor activity has finished.
Example: Concrete must cure (finish) before framing can begin (start).
2. Start-to-Start (SS) - A successor activity cannot start until its predecessor activity has started.
Example: Quality inspection (successor) can begin once production (predecessor) has started.
3. Finish-to-Finish (FF) - A successor activity cannot finish until its predecessor activity has finished.
Example: System testing cannot finish until all coding work has finished.
4. Start-to-Finish (SF) - A successor activity cannot finish until its predecessor activity has started.
Example: The current shift cannot end until the next shift begins.
How Dependencies Affect the Critical Path
The critical path is calculated by analyzing all activity sequences through the network diagram. Dependencies determine:
• Which activities can be performed in parallel
• Which activities must be performed sequentially
• The early start, early finish, late start, and late finish dates for each activity
• The total float or slack for each activity
• The overall project duration
Categories of Dependencies
Mandatory Dependencies (Hard Logic)
• Physical limitations that cannot be changed
• Example: You must pour a foundation before building walls
Discretionary Dependencies (Soft Logic)
• Based on best practices or preferences
• Example: Choosing to complete design before starting procurement
External Dependencies
• Dependencies on elements outside the project team's control
• Example: Waiting for regulatory approval before proceeding
Internal Dependencies
• Dependencies between activities within the project team's control
• Example: Designing before building
Dependency Determination Process
1. Identify activities - Break down the project into manageable activities
2. Sequence activities - Determine the logical order
3. Select dependency type - Choose the appropriate relationship (FS, SS, FF, SF)
4. Document dependencies - Create a network diagram or precedence diagram
5. Review for completeness - Ensure all activities have at least one predecessor and successor (except for the first and last activities)
Lead and Lag Time in Dependencies
Lead Time allows a successor activity to start earlier than it normally would according to the dependency type. It's an acceleration or overlap of activities.
Example: In a FS relationship with a 5-day lead, the successor can start 5 days before the predecessor finishes.
Lag Time adds a delay between activities. It extends the waiting time between the predecessor and successor.
Example: In a FS relationship with a 3-day lag, the successor must wait 3 days after the predecessor finishes before it can start.
Common Pitfalls in Dependency Determination
• Creating circular dependencies where activities depend on each other
• Overusing discretionary dependencies, creating unnecessary restrictions
• Using the wrong dependency type for the relationship
• Failing to account for external dependencies
• Creating too many dependencies, making the schedule rigid
• Not considering resource availability when determining dependencies
Exam Tips: Answering Questions on Dependency Determination and Types in CPM
1. Know the four dependency types cold - Be able to identify and explain FS, SS, FF, and SF relationships.
2. Understand the different categories - Be prepared to distinguish between mandatory, discretionary, external, and internal dependencies.
3. Practice network diagramming - Many exam questions involve interpreting or creating network diagrams.
4. Calculate with lead and lag - Know how to incorporate lead and lag times into schedule calculations.
5. Apply critical thinking - For scenario-based questions, think about the practical implications of dependencies in real project situations.
6. Watch for relationship identification - Be ready to identify the correct dependency type from a description of two activities.
7. Understand dependency impacts - Know how changing a dependency affects the critical path and project duration.
8. Recognize improper dependencies - Be able to spot invalid dependencies like circular relationships.
9. Connect to other knowledge areas - Relate dependencies to risk management, resource management, and scope management.
10. Use process of elimination - For multiple-choice questions, eliminate answers that are completely illogical before selecting from remaining options.
Remember that dependency determination is the foundation of schedule development. On the exam, you'll need to demonstrate that you understand not just the technical aspects of dependencies, but also their practical application in creating realistic and manageable project schedules.
PMI-SP - Dependency Determination and Types in CPM Example Questions
Test your knowledge of Dependency Determination and Types in CPM
Question 1
Which of the following best describes a logical relationship in a CPM network where one activity must be delayed by a specific duration after another activity starts?
Question 2
In a Critical Path Method (CPM) network diagram, which statement best describes a Finish-to-Start (FS) dependency relationship?
Question 3
In a Critical Path Method (CPM) analysis, what best describes a mandatory dependency (also known as hard logic)?