Program Evaluation and Review Technique (PERT)

5 minutes 5 Questions

The Program Evaluation and Review Technique (PERT) is a statistical tool used to model the tasks involved in completing a project, particularly when time estimates are uncertain. PERT uses probabilistic time estimates to calculate the expected duration of each activity and the overall project. It involves three-time estimates for each task: optimistic (the shortest time in which the activity can be completed), most likely (the completion time having the highest probability), and pessimistic (the longest time the activity might take). By applying these estimates, PERT calculates the expected time for each task using the formula: (Optimistic + 4×Most Likely + Pessimistic) ÷ 6. This approach acknowledges the inherent uncertainty in project scheduling and provides a more realistic timeline. PERT charts visually represent task sequences and dependencies, helping project managers to identify the critical path and analyze the time variability within the project schedule. This technique is particularly useful in research and development projects where activity durations are difficult to predict. By incorporating the variability and risk of time estimates, PERT enhances the planning and decision-making process, enabling project managers to anticipate potential delays and implement contingency plans. It ultimately contributes to more effective schedule development by providing a probabilistic assessment of project completion times.

Program Evaluation and Review Technique (PERT): A Comprehensive Guide

Introduction to PERT

Program Evaluation and Review Technique (PERT) is a statistical tool used in project management for analyzing and representing the tasks involved in completing a project. Developed by the U.S. Navy in the 1950s for the Polaris submarine missile program, PERT has become an essential scheduling methodology for complex projects.

Why PERT is Important

PERT is crucial in project management for several reasons:

• It helps manage uncertainty in project scheduling
• It identifies critical paths and potential bottlenecks
• It allows for realistic time estimations in complex projects
• It provides a visual representation of task dependencies
• It enables better resource allocation and risk management

What is PERT?

PERT is a statistical technique that analyzes the tasks involved in completing a project, especially the time needed to complete each task and the minimum time required to complete the total project. It's particularly useful in projects where activity times are uncertain.

PERT uses three time estimates for each activity:

Optimistic time (O): The minimum possible time required
Most likely time (M): The most probable time required
Pessimistic time (P): The maximum possible time required

These three estimates are used to calculate the expected time (TE) using the formula:

TE = (O + 4M + P) ÷ 6

How PERT Works

1. Create a list of all activities required to complete the project
2. Determine dependencies between activities
3. Create a network diagram showing the sequence of activities
4. Estimate the three time values (O, M, P) for each activity
5. Calculate the expected time for each activity using the PERT formula
6. Identify the critical path, which represents the longest path through the network and determines the minimum project duration
7. Calculate slack for each activity to determine flexibility
8. Determine standard deviation to understand the uncertainty

Variance in PERT is calculated as: [(P - O)/6]²

PERT vs. CPM (Critical Path Method)

While often mentioned together, PERT and CPM have distinct differences:

• PERT uses probabilistic time estimates (three-point estimation)
• CPM uses deterministic time estimates (single-point estimation)
• PERT focuses on time management with uncertainty
• CPM balances time and cost and allows for time-cost trade-offs

Exam Tips: Answering Questions on PERT

1. Memorize the PERT formula: Know that TE = (O + 4M + P) ÷ 6 and be prepared to apply it

2. Understand variance calculation: Remember the formula [(P - O)/6]² to calculate variance

3. Know how to identify the critical path: The critical path is the longest path through the network and has zero float

4. Be clear on terminology:
• Float/Slack: Amount of time an activity can be delayed
• Forward Pass: Calculating early start and early finish times
• Backward Pass: Calculating late start and late finish times

5. Practice calculations: Be prepared for questions requiring numerical solutions

6. Distinguish PERT from other techniques: Know how PERT differs from CPM, Gantt charts, and other scheduling methods

7. Understand probability concepts: PERT assumes a beta distribution for time estimates

8. Application scenarios: Be ready to identify when PERT is most appropriate (complex projects with uncertain time estimates)

9. Network diagram interpretation: Practice reading and analyzing PERT network diagrams

10. Look for key phrases in exam questions such as "uncertain durations," "three-point estimation," or "probabilistic scheduling" that indicate PERT is the appropriate technique

PERT is an invaluable tool in the PMI-SP certification arsenal, particularly when dealing with projects that have significant uncertainty in activity durations. By understanding how to apply PERT effectively, project schedule professionals can better manage complex projects and more accurately predict completion times.

Test mode:
Go Premium

PMI Scheduling Professional Preparation Package (2025)

  • 3429 Superior-grade PMI Scheduling Professional practice questions.
  • Accelerated Mastery: Deep dive into critical topics to fast-track your mastery.
  • Unlock Effortless PMI-SP preparation: 5 full exams.
  • 100% Satisfaction Guaranteed: Full refund with no questions if unsatisfied.
  • Bonus: If you upgrade now you get upgraded access to all courses
  • Risk-Free Decision: Start with a 7-day free trial - get premium features at no cost!
More Program Evaluation and Review Technique (PERT) questions
12 questions (total)