Program Evaluation and Review Technique (PERT)

5 minutes 5 Questions

The Program Evaluation and Review Technique (PERT) is a statistical tool used to model the tasks involved in completing a project, particularly when time estimates are uncertain. PERT uses probabilistic time estimates to calculate the expected duration of each activity and the overall project. It i…

Test mode:
PMI-SP - Program Evaluation and Review Technique (PERT) Example Questions

Test your knowledge of Program Evaluation and Review Technique (PERT)

Question 1

In a PERT diagram, when activities have multiple parallel paths, which path should receive the most attention from the project manager?

Question 2

In PERT analysis, what is the correct formula to calculate expected duration (Te)?

Question 3

When conducting PERT estimations, what is the primary benefit of using three-point estimates?

More Program Evaluation and Review Technique (PERT) questions
12 questions (total)