Activity Sequencing

5 minutes 5 Questions

Activity Sequencing is the process of identifying the relationships and dependencies among the project activities, and then arranging them in the logical order of execution. This helps project managers to develop a coherent project schedule, establish realistic deadlines, and allocate resources eff…

Test mode:
PMP - Activity Sequencing Example Questions

Test your knowledge of Activity Sequencing

Question 1

You are managing the creation of a new mobile app, The design team must finalize the app's flow and design before coding can start. However, market research and content creation for the app can begin after the app's overall concept is decided but before the design is finalized. What type of activity sequencing applies here?

Question 2

A project manager is working on a project with several dependencies, including internal and external resources. It is crucial to manage these dependencies effectively. Which tool or technique can help the project manager manage the dependencies?

Question 3

You are managing an IT project. The installation of the server can start after the software and hardware have been purchased, but the network setup cannot start until the server installation has completed. Simultaneously, the workstations setup can begin before the network setup starts but should finish after the network setup. How will you sequence these activities?

More Activity Sequencing questions
33 questions (total)