Critical Path Method

5 minutes 5 Questions

The Critical Path Method (CPM) is a widely used technique in project management for determining the longest sequence of activities that must be completed on time for the project to finish on schedule. The critical path represents the shortest possible duration to complete the project and serves as …

Test mode:
PMP - Critical Path Method Example Questions

Test your knowledge of Critical Path Method

Question 1

A software development project has multiple paths. Path A has a duration of 35 days, Path B has a duration of 25 days, Path C has a duration of 30 days, and Path D has a duration of 42 days. Which path is the critical path?

Question 2

In a manufacturing project with tasks A (4 days), B(3 days), C(5 days), and D(6 days) where A and B can commence concurrently but must be completed prior to C which precedes D. If Task C duration is extended by 2 days, how would that affect the project end date?

Question 3

In a project, there are tasks A, B, and C. Task A (3 days) precedes Task B (4 days) and C (5 days) can be started once Task B is completed. If Task C is delayed by 2 days, how does this change the critical path duration?

More Critical Path Method questions
116 questions (total)