Capture and Examine Issues

5 minutes 5 Questions

In PRINCE2 7, the 'Capture and examine issues and risks' activity within the Controlling a Stage process is the primary mechanism for managing deviations and changes. An issue is defined as any relevant event that has happened, was not planned, and requires management action. They are categorized as Requests for Change, Off-specifications, or Problems/Concerns. The process involves two distinct steps: 1. **Capture**: The Project Manager must formally record the issue. Minor issues may go into the Daily Log, while formal issues are recorded in the Issue Register. An Issue Report is created to describe the issue clearly. This step ensures that nothing is lost and an audit trail is maintained. 2. **Examine**: The Project Manager acts to understand the issue's impact. This involves assessing how the issue affects the six performance targets of the current Stage Plan and the overall Project Plan: time, cost, quality, scope, benefits, and risk. Crucially, the Project Manager checks the impact against the Business Case and sustainability targets. During examination, the Project Manager prioritizes the issue (often using MoSCoW) and assesses its severity. The critical decision point is checking against **tolerances**. If the proposed solution to the issue can be executed within the agreed Stage Tolerances, the Project Manager can take corrective action. However, if the issue is forecasted to breach stage tolerances, it becomes an 'Exception.' In this case, the Project Manager cannot decide unilaterally; they must escalate to the Project Board via an Exception Report to seek direction.

Guide: Capture and Examine Issues (Controlling a Stage) - PRINCE2 Practitioner v7

Overview
In the PRINCE2 v7 Controlling a Stage process, the Project Manager is responsible for day-to-day management, which includes handling unplanned events. Capture and Examine Issues is the specific activity where the Project Manager reviews issues and risks that have arisen, ensuring they are properly understood before any action is taken.

Why is it Important?
This activity is the defense against scope creep and uncontrolled change. It ensures that decisions are data-driven rather than reactive. By capturing and examining issues, the Project Manager ensures that the impact on the project's six performance targets (Time, Cost, Quality, Scope, Risk, and Benefits) and the Business Case is fully assessed prior to implementation.

How it Works: The Process
This activity typically follows the initial steps of the Issue and Change Control procedure:
1. Capture: The issue is formally recorded in the Issue Register. If the issue is handled informally, it may be noted in the Daily Log, but for Practitioner exams, usually assume formal registration.
2. Categorize: The Project Manager must determine the type of issue:
- Request for Change (RFC): A proposal for a change to a baseline.
- Off-specification: Something currently missing or incorrect (a failure to meet requirements).
- Problem/Concern: Any other issue that the PM needs to resolve or escalate.
3. Assess: The PM performs an Impact Analysis to see how the issue affects the Stage Plan, Project Plan, Business Case, and Project Risks. Priority and severity are assigned at this stage.

Exam Tips: Answering Questions on Capture and Examine Issues
To answer Practitioner questions correctly, look for these specific cues in the scenario:

1. Classify the Issue Correctly
Many questions ask you to identify how to log an event. If the customer asks for a new button on a website, answer Request for Change. If the supplier calls to say the server is broken, answer Off-specification. If a team member is worried about a deadline, answer Problem/Concern.

2. Distinguish 'Examining' from 'Proposing'
Be careful with the timeline. If the question asks what the PM should do immediately after an issue is raised, look for answers related to Impact Analysis or updating the Issue Register. Do not select answers involving 'implementing a fix' or 'updating the Plan' yet—those actions happen in the subsequent activity (Propose Corrective Action).

3. Check Authority Levels
Part of 'Examining' is determining if the issue is within the Project Manager's tolerance. If the scenario suggests the change is expensive or risky, the correct answer usually involves preparing information for the Change Authority or Project Board, rather than the PM making the decision alone.
Test mode:

PRINCE2 Practitioner - Capture and Examine Issues Example Questions

Test your knowledge of Capture and Examine Issues

Question 1

A senior user asks the project manager to add automated returns processing to the new warehouse management system being delivered for a retailer. The project manager records the request for change in the issue register. They then estimate the extra cost and the delay, and check whether the expected benefits would still outweigh them. Only then do they pass the request to the change authority. Which principle is the project manager chiefly applying, and why?

Question 2

A team manager reports that the kitchen extraction unit installed for the restaurant chain's new branch exceeds the noise limit in its product description. Project support records it in the issue register as an off-specification. The senior supplier offers specialist advice on possible fixes. Within the 'Controlling a stage' process, which role is responsible for assessing the impact of this issue on the stage plan, project plan and business case?

Question 3

The project is in stage 3 of replacing a retailer's warehouse management system. A team manager reports that a test environment password has expired, which will delay one test by half a day. The project manager confirms that the delay is within stage tolerance and changes no baselined product. The project manager resolves it with project support and records it in the daily log. Is this an appropriate application of the 'capture and examine issues' activity, and why?

More Capture and Examine Issues questions
11 questions (total)