Wideband Delphi Technique
The Wideband Delphi technique encourages anonymous, independent estimation by each team member. The process typically involves iteration until a consensus has been reached. Each estimator independently estimates then all estimates are revealed at once. Discussion follows where information is exchanged about each estimate. The facilitator might provide an average for guidance but doesn’t provide the ‘right’ answer. The iterations can continue until consensus is achieved, though it isn't enforced. This can be incredibly valuable as it manages cognitive biases like anchoring, where early estimates can unduly influence future ones.
Guide: Wideband Delphi Technique for PSM I Exam
The principle of this technique is to use a panel of experts who anonymously offer estimates on a specific task. These estimates are reviewed as a group, after which, each panel member can adjust their estimate based on what was discussed.
The process continues until a consensus is reached.
Exam Tips: Answering Questions on Wideband Delphi Technique
1. Understand the process: Make sure you can explain the step-by-step process of this technique.
2. Recognize its benefits: Remember that its main benefits are anonymity and reduced pressure, leading to more accurate estimates.
3. Know when to use it: You should be able to identify situations in which it would be advantageous to use the Wideband Delphi technique.
4. Practice: Answer a few practice questions or case studies to familiarize with how these questions might be posed in the exam.
PSM I - Wideband Delphi Technique Example Questions
Test your knowledge of Wideband Delphi Technique
Question 1
During a Wideband Delphi estimation session, one of the team members always offers her estimate last, frequently influencing the other team members. As the Scrum Master, how should you address the situation?
Question 2
Your team has used the Wideband Delphi estimation technique for estimating the backlog items. A member has consistently been estimating higher than the rest of the team, pushing the overall estimates upwards. What is the best approach to this scenario?
Question 3
During a Wideband Delphi estimation session, team members found the re-estimation process to be tedious and time-consuming as they failed to reach a consensus after several rounds. How should the Scrum Master address this?