Sprint Backlog

5 minutes 5 Questions

The Sprint Backlog is the set of Product Backlog items selected for the Sprint, plus a plan for delivering the product Increment and achieving the Sprint Goal. The Sprint Backlog is a forecast by the Developers of what functionality will be in the next Increment and the work needed to deliver that functionality into a 'Done' Increment. The Sprint Backlog is a plan with enough detail to understand changes in progress during the Sprint. The Developers modify the Sprint Backlog throughout the Sprint, and the Sprint Backlog emerges during the Sprint.

Guide: Understanding and Answering Questions on Sprint Backlog

The Sprint Backlog is an important part of Scrum methodology. It is a list of tasks that the development team needs to work on during the next sprint. The purpose of the Sprint Backlog is to provide a clear understanding of the work that needs to be done.

What is a Sprint Backlog
A Sprint Backlog is a set of items selected from the product backlog to be worked on during the next sprint, which are then broken down into task. It provides the team with a structured approach to achieving the sprint goal.

How it Works
The Sprint Backlog is created during the Sprint Planning meeting. The development team selects items from the product backlog that they think they can complete during the next sprint. Then, these items are broken down into tasks, and the tasks are transferred to the Sprint Backlog.

Why it is Important
The Sprint Backlog is important because it gives the team a clear understanding of their tasks for the next sprint. This helps keep the team focused, and improves overall productivity.

Exam Tips: Answering Questions on Sprint Backlog
- Understand the definition and purpose of the Sprint Backlog.
- Be familiar with how a Sprint Backlog is created and used in Scrum methodology.
- Be prepared to explain the importance of the Sprint Backlog in an effective Scrum process.
- Be able to explain what happens if items are not completed by the end of the sprint (They can go back to the product backlog for future consideration).
- Remember that changes to the Sprint Backlog should be minimized once the Sprint has started.
Test mode:

PSM I - Sprint Backlog Example Questions

Test your knowledge of Sprint Backlog

Question 1

You are a Scrum Master, the team has less work in the Sprint Backlog than planned, but refuses to add more items. The team is confident they won't complete additional items due to technical complexity. What is the best approach in this situation?

Question 2

As a Scrum Master, the team is struggling to manage the Sprint Backlog. What could you introduce to help the team?

Question 3

The team has fallen into the habit of frequently updating the Sprint Backlog towards the end of the Sprint. As a Scrum Master, how would you address this?

More Sprint Backlog questions
36 questions (total)