Learn Initiating a Project Process (PRINCE2 Practitioner) with Interactive Flashcards

Master key concepts in Initiating a Project Process through our interactive flashcard system. Click on each card to reveal detailed explanations and enhance your understanding.

Prepare Risk Management Approach

In the context of the Initiating a Project process within PRINCE2 7, preparing the Risk Management Approach is a foundational activity dedicated to defining how uncertainty will be governed and controlled throughout the project lifecycle. This activity ensures that the project management team and stakeholders possess a shared understanding of the specific standards and procedures required to manage threats and opportunities effectively. The Project Manager is responsible for creating this document, often tailoring it from existing corporate or programme standards to suit the specific scale and complexity of the project. The approach details the specific techniques for identifying and assessing risks, establishing the scales for probability and impact to ensure consistent estimation. It defines the project's risk tolerance and risk appetite, setting the boundaries for what level of risk is acceptable before escalation to the Project Board is required. Crucially, this activity assigns clear roles and responsibilities, identifying who is responsible for owning risks and executing response actions. It also establishes the reporting requirements and the timing of risk management activities, such as scheduled reviews or workshops. The document may also define a risk budget specifically set aside for funding risk responses. Once drafted, the Risk Management Approach is reviewed by Project Assurance and ultimately approved by the Project Board as part of the Project Initiation Documentation (PID). This structured preparation moves risk management from ad-hoc firefighting to a proactive, controlled discipline essential for project success.

Prepare Quality Management Approach

In the context of the PRINCE2 7 Initiating a Project process, the activity to 'Prepare the Quality Management Approach' is pivotal for establishing how the project will ensure its products are fit for purpose. This approach defines the quality standards, procedures, techniques, and responsibilities that will be applied throughout the project lifecycle to verify that outputs meet agreed requirements.

The primary goal is to convert the customer’s quality expectations and acceptance criteria, originally outlined in the Project Brief, into a concrete plan of action. This involves determining which quality standards (corporate, international, or regulatory) apply and selecting appropriate tools and techniques for quality planning, control, and assurance. For instance, the approach details whether the project will utilize formal quality reviews, inspections, automated testing, or piloting strategies.

A key aspect of this activity is defining roles and responsibilities—specifically clarifying who is responsible for the specification, creation, review, and approval of products to ensure independence between the creator and the reviewer. Furthermore, it establishes the protocols for the Quality Register, a dynamic log used to track the status of quality events.

Under PRINCE2 7, this approach also explicitly considers the 'People' element, ensuring the project culture supports a quality-focused mindset, and aligns with organizational sustainability targets. The Project Manager collaborates with Project Assurance and key stakeholders (such as the Senior User and Senior Supplier) to draft this document. Once approved, it forms a vital component of the Project Initiation Documentation (PID), serving as the baseline against which all quality activities are measured to ensure the project delivers value and benefits.

Prepare Change Control Approach

In the context of the PRINCE2 7 'Initiating a Project' process, the activity to 'Prepare the Change Control Approach' is fundamental to establishing governance over project baselines. Its primary purpose is to define the specific mechanisms the project will use to handle issues (unexpected events), changes (requests to alter the baseline), and configuration management (tracking and protecting products). Without this robust framework, projects are susceptible to scope creep and loss of asset integrity.

The Project Manager creates this approach by first reviewing corporate or programme standards to ensure alignment. The resulting document details two distinct but related procedures. First, the 'Configuration Management Procedure' outlines how project products (assets) will be identified, version-controlled, stored, and protected. This ensures the team always works with the correct versions of documents or outputs.

Second, the 'Issue and Change Control Procedure' defines the step-by-step process for capturing, examining, proposing, deciding upon, and implementing changes. This includes establishing scales for priority (e.g., MoSCoW) and severity to ensure consistent assessment across the team.

A critical aspect of this activity is defining roles and responsibilities, specifically the 'Change Authority.' The Project Board must decide if they will make all change decisions or delegate authority for changes within specific limits (e.g., budget or impact thresholds) to a separate group or individual. Additionally, the role of Project Support is defined regarding the maintenance of the Issue Register and Configuration Item Records.

Ultimately, this approach becomes a component of the Project Initiation Documentation (PID), providing a clear, agreed-upon rulebook for maintaining the project's stability and justification amidst inevitable changes.

Set Up Project Controls

In the PRINCE2 7 'Initiating a Project' process, the activity 'Set Up Project Controls' is pivotal for establishing the governance mechanisms required to monitor progress and maintain the project's viability. The primary objective is to define how the project will be managed, ensuring the Project Board can exercise 'management by exception' without being overloaded by daily details.

During this activity, the Project Manager defines the specific level of control required, balancing the need for oversight with the administrative effort. Key elements involve establishing tolerances for the seven performance targets: time, cost, quality, scope, risk, benefit, and sustainability. These tolerances set the boundaries of authority for the Project Manager; if these are forecast to be exceeded, an exception must be escalated to the Project Board.

Furthermore, this activity establishes the reporting and decision-making structures. This includes determining the number and length of management stages based on the planning horizon and risk profile. It also defines the frequency and format of communication flows, such as Highlight Reports (from Project Manager to Board) and Checkpoint Reports (from Team Manager to Project Manager).

The Project Manager also confirms mechanisms for issue and change control to handle deviations or requests formally. These controls are integrated into the Project Plan and summarized in the Project Initiation Documentation (PID). Effectively setting up these controls ensures all stakeholders understand their decision-making authority, how performance is tracked, and the specific triggers that require senior management intervention, thereby securing a controlled environment for project delivery.

Create Project Plan

In the context of the PRINCE2 7 'Initiating a Project' process, creating the Project Plan is a critical activity led by the Project Manager. Its primary objective is to transform the high-level outline from the Project Brief into a detailed, baselined roadmap that specifies how, when, and at what cost the project's products will be delivered. This plan constitutes a major part of the Project Initiation Documentation (PID) and is essential for obtaining Project Board authorization to proceed.

The creation of the Project Plan utilizes the PRINCE2 product-based planning technique to ensure a focus on outputs. This involves four specific steps: writing the Project Product Description to define the final deliverable and its acceptance criteria; creating a Product Breakdown Structure (PBS) to visualize the hierarchy of components; defining Product Descriptions for lower-level deliverables; and producing a Product Flow Diagram (PFD) to map the sequence of production.

Following product definition, the Project Manager identifies the activities, resources, and durations required to build these products. This leads to the development of a schedule and budget, including the calculation of the project's timeline and cash flow. The plan also incorporates specific management stages, which serve as control points for the Project Board. Furthermore, the Project Plan must align with the management approaches (Risk, Quality, Change, and Sustainability) defined earlier in the initiation process. Once approved, this plan becomes the master baseline against which performance, progress, and continued business justification are measured throughout the project lifecycle.

Refine Business Case

In the context of the PRINCE2 7 'Initiating a Project' (IP) process, refining the Business Case is a pivotal activity that transforms the initial justification into a firm baseline for the project. During the earlier 'Starting Up a Project' process, an Outline Business Case was sufficient to authorize the initiation stage. However, to authorize the main delivery stages, the Project Board requires a detailed Full Business Case based on concrete planning data.

The primary objective is to justify the project's value. This activity relies heavily on data generated during the 'Create the Project Plan' activity. The Project Manager updates the outline with detailed costs and timescales derived specifically from the newly created Project Plan, as one cannot accurately determine viability without understanding the specific resources, time, and costs required to deliver the products.

Key actions within this activity include:
1. Investment Appraisal: Refining calculations such as Return on Investment (ROI) and Net Present Value to demonstrate value for money.
2. Risk Analysis: Cross-referencing the Risk Register to ensure that major risks do not undermine the expected benefits.
3. Benefits and Dis-benefits: Detailed quantification of the positive outcomes and any negative consequences.
4. Sustainability: Ensuring the justification aligns with the organization's sustainability targets, a focus emphasized in PRINCE2 7.

Parallel to this, the 'Benefits Management Approach' is developed to define exactly how and when benefits will be measured. The output—the Full Business Case—becomes a central component of the Project Initiation Documentation (PID). It serves as the benchmark for the 'continued business justification' principle, assessed at every Stage Boundary to ensure the project remains desirable, viable, and achievable.

Assemble Project Initiation Documentation

In the context of the PRINCE2 7 'Initiating a Project' process, the activity to 'Assemble the Project Initiation Documentation' (PID) is the focal point where the solid foundation of the project is finalized. This activity involves consolidating all the management products created during the initiation stage into a single, logical set of documents. The PID acts as the primary reference point for the project and serves as the 'contract' between the Project Manager and the Project Board.

The assembly process involves gathering the refined Business Case, the detailed Project Plan, and the various Management Approaches (such as Risk, Quality, Change, and Communication). It also includes the Project Controls and the specific Project Management Team Structure. Crucially, under PRINCE2 7, this documentation must explicitly detail how the methodology has been tailored to suit the specific context and scale of the project, ensuring the governance is appropriate.

The purpose of the PID is to ensure that the project has a sound basis before the Project Board commits to significant expenditure. It defines what the project aims to achieve, why it is needed, who will be involved, how and when it will be delivered, and how risks and issues will be managed. By creating this baseline, the project team establishes the criteria against which performance will be assessed throughout the project lifecycle.

Once assembled, the PID is presented to the Project Board. Its approval authorizes the Project Manager to proceed to the first delivery stage. Without a signed-off PID, the project proceeds without authorized boundaries, significantly increasing the risk of failure.

More Initiating a Project Process questions
280 questions (total)