Communication Gaps and Stakeholder Management

Mitigating communication issues as they emerge (feedback loops, overcoming resistance, action plans) and managing stakeholders: identification and assessment for the communication strategy, and the role of culture.

5 minutes 5 Questions

In the PMI Construction Professional (PMI-CP) framework, communication gaps and stakeholder management are closely linked competencies for delivering complex built environment projects. Construction projects involve many stakeholders, including owners, designers, contractors, subcontractors, suppli…

Test mode:

PMI-CP - Communication Gaps and Stakeholder Management Example Questions

Test your knowledge of Communication Gaps and Stakeholder Management

Question 1

How does the stakeholder register differ in purpose from the stakeholder engagement plan on a construction project?

Question 2

On a construction management at risk project, the owner's site representative has agreed in field meetings to several minor finish substitutions requested by trade partners. The owner's project manager later reversed two of them because they exceeded the representative's delegated authority. Trade partners now doubt that any field agreement will hold, and some have started delaying work until decisions are confirmed. Which action should the contractor's project manager take to BEST restore trust in field commitments?

Question 3

A project manager is identifying stakeholders for a pipeline across farmland. Easements are signed with every landowner and logged in the register, but they grant access only subject to existing occupancy rights. Survey crews report four facts. Several parcels are worked by tenants on seasonal leases. A water board has already licensed the canal crossing. A farmers' cooperative wants updates. Some parcels carry mortgages. Mobilization is in six weeks. Which addition to the register is MOST critical now?

More Communication Gaps and Stakeholder Management questions