PMI-CP - Contract Lifecycle and Delivery Methods Example Questions
Test your knowledge of Contract Lifecycle and Delivery Methods
Question 1
A unit price pipeline contract pays trench excavation per linear metre, with the rate priced for depths up to 2 m. An owner design revision lowers the invert, so a 300 m stretch must now be dug to 4 m and needs heavier shoring. The contract says bid rates apply only to work of similar character and conditions. Otherwise, a new rate is built from the bid rate breakdown. The contractor proposes measuring that stretch as 600 m. How should the project manager value this work?
Question 2
A contract defines substantial completion as the point when the facility can be occupied for its intended use with only minor items outstanding. It requires the owner's project manager to respond to a contractor's request for a substantial completion certificate within 7 days. At the joint inspection, the fire alarm system has not passed its required acceptance test, and several rooms need paint touch-ups. What should the project manager do?
Question 3
On a unit price contract, the final account is valued on quantities actually executed, as measured jointly by both parties while the work proceeds. At close-out, the contractor's final statement prices the earthworks line using the bill of quantities estimate. That estimate exceeds the signed joint measurement sheets by 8%. The contractor argues the bill figure was agreed at award. How should the project manager value this line in the final account?