Interface Management
Interface points between packages, interface classification on mega projects, the leading frameworks and systems, designing and timing the interface management practice, leading and monitoring the plan, and the communication, relationship and negotiation skills it needs.
In the PMI Construction Professional (PMI-CP) framework, Interface Management is the structured discipline of identifying, documenting, coordinating, and controlling the points where different parties, scopes, systems, or physical elements of a construction project meet and depend on one another. L…
PMI-CP - Interface Management Example Questions
Test your knowledge of Interface Management
Question 1
During Front End Planning for a pumping station, the team plans to tender the foundations package before procuring the pumps. The draft interface register shows that the foundation design depends on pump loads and anchor bolt details, and only the selected pump supplier can certify those figures. Which approach BEST addresses this interface point?
Question 2
On a hospital project, the interface governance plan sets a monthly interface coordination meeting. The project has now entered fit-out, and many interface points between the mechanical, electrical and ceiling packages have need dates two to three weeks out. Several interface agreements reached at recent monthly meetings arrived after the installation sequence had already needed them, which forced crews to resequence work. Which approach BEST addresses this?
Question 3
On a highway interchange, the owner holds separate contracts with a bridge contractor and a utility relocation contractor. The two designers have fully dimensioned and agreed the duct bank sleeves through the abutment. However, the utility contractor will not commit to a crew sequence. It states that it has no obligation to the bridge contractor, and the two contracts set different site access terms. What should the interface manager do NEXT?