Within the PMI Construction Professional (PMI-CP) credential, Project Governance and Performance covers the structures, decision rights, and measurement practices that keep a built environment project aligned with organizational strategy, contractual obligations, and stakeholder expectations. Gover…

Test mode:

PMI-CP - Project Governance and Performance Example Questions

Test your knowledge of Project Governance and Performance

Question 1

A governance charter lets the project manager approve changes up to $75,000. It states that delegated limits may be passed to another person only by written designation from the sponsor. Before a three-week leave, the project manager emails the site deputy: "approve anything under $75,000 while I'm away." The contractor then submits a $40,000 change that the deputy has already priced and evaluated against the project outcomes. What should the deputy do?

Question 2

On a public-private partnership hospital, the project board (sponsor, lenders' technical advisor and design-build contractor) meets weekly through commissioning. It signs off each building system after an independent commissioning agent witnesses its tests. The facility operator's requirements were confirmed at design and have not changed, but the operator attends board meetings only as an observer. Several systems the board accepted are now being rejected by the operator at handover trials, reopening work and delaying occupancy. Which governance gap BEST explains the recurring rejections?

Question 3

On a design-build office project, the scope governance plan states that owner review comments on design submittals are checked against the owner's project requirements. Any comment that goes beyond those requirements is logged for the change board. At the 60% design review, the owner's facility staff mark up upgraded finishes and add a second server room. The design-builder's project manager confirms that both items exceed the owner's project requirements. What should the project manager do NEXT?