Scope and Change Order Management

Defining scope around project outcomes and maturing it through revisions, a robust and well-timed change order process (including agile handling and the use of technology), evaluating changes against core outcomes, and the scope evaluation and management tools (value engineering, cost-benefit analysis).

5 minutes 5 Questions

In the PMI Construction Professional (PMI-CP) framework, Scope and Change Order Management covers how construction teams define, control, and adjust the work required to deliver a project, while protecting cost, schedule, quality, and contractual relationships. Scope management starts with clearly …

Test mode:

PMI-CP - Scope and Change Order Management Example Questions

Test your knowledge of Scope and Change Order Management

Question 1

In a work breakdown structure for a built environment project, what does the code of accounts provide?

Question 2

On a lump-sum contract, the roofing subcontractor prefers a membrane system its crews already know. The contractor proposes that system in place of the specified product at no change to the contract sum. The change clause lets the owner accept or reject contractor-initiated substitutions. Which consideration should govern the owner's project manager's recommendation on the proposal?

Question 3

During Front End Planning for a school renovation, the owner's operations team assumes that loose furniture and classroom IT equipment are part of the project. The design team's draft scope statement does not mention either item, and the finance group has budgeted only for building works. The project manager wants to prevent a scope dispute later. Which action BEST achieves this?

More Scope and Change Order Management questions