Contingency Planning and Reserves

Allocating resources for risk responses.

This topic covers the development of contingency plans and the establishment of time and cost reserves to address identified risks.
5 minutes 5 Questions

Contingency Planning and Reserves are critical components of risk management in project contexts, specifically addressed within the PMI Risk Management Professional framework. Contingency Planning involves developing predetermined action plans that will be implemented if identified risks materiali…

Concepts covered: Management Reserves, Contingency Reserves, Schedule Contingency, Reserve Analysis, Fallback Planning, Workarounds, Contingency Planning, Risk Triggers, Buffer Management

Test mode:
PMI-RMP - Contingency Planning and Reserves Example Questions

Test your knowledge of Contingency Planning and Reserves

Question 1

When allocating Schedule Contingency in a project with multiple parallel activities, which approach is most effective?

Question 2

How should Schedule Contingency be distributed in a project where all critical path activities have equal risk exposure?

Question 3

In a project with unexpected risk events materializing, what is the best approach to reassess Schedule Contingency?

More Contingency Planning and Reserves questions
98 questions (total)