Issues Practice

Apply issue and change control management.

Covers issue management approach, issue register, and issue reports. Focuses on types of issues (change requests, off-specifications, problems/concerns, business opportunities), change control processes, baseline management, delegating authority for changes, and change budgets. Renamed from 'Change' theme in V6 to better reflect the broader scope of issue handling.
5 minutes 5 Questions

In the context of PRINCE2 7, the Issues practice is the mechanism used to identify, assess, and control any event that has happened, was not planned, and requires management action. Its purpose is to ensure that the project remains aligned with the Business Case by effectively managing changes to b…

Concepts covered: Issue Management Approach, Issue Register, Issue Report, Types of Issues, Change Control Process, Baseline Management, Change Budget and Authority

Test mode:
PRINCE2 Practitioner - Issues Practice Example Questions

Test your knowledge of Issues Practice

Question 1

A project to implement a new customer relationship management system is in Stage 3. The Team Manager reports that a software module purchased from an external vendor is incompatible with the existing database architecture, requiring significant rework. The Project Manager needs to capture this situation formally. The vendor has confirmed they can provide a modified version in 4 weeks, but this will delay the planned integration testing. The Project Manager estimates the impact on the project schedule and budget before deciding on the next steps. Which statement best describes how the Project Manager should document this situation in the Issue Report?

Question 2

A construction project is entering its final stage when the Project Manager discovers that three separate issues logged in the Issue Register over the past two months are actually symptoms of a single underlying problem: insufficient foundation specifications provided by the original design team. Issue #47 concerns delays in concrete pouring, Issue #52 addresses unexpected ground settlement, and Issue #58 relates to structural engineer concerns about load-bearing capacity. All three issues remain open with different team members assigned to investigate them separately. What should the Project Manager do to optimize the management of these issues?

Question 3

What is the primary distinction between the change budget and change authority in project change control?

More Issues Practice questions
214 questions (total)