Issues Practice
Apply issue and change control management.
In the context of PRINCE2 7, the Issues practice is the mechanism used to identify, assess, and control any event that has happened, was not planned, and requires management action. Its purpose is to ensure that the project remains aligned with the Business Case by effectively managing changes to b…
Concepts covered: Issue Management Approach, Issue Register, Issue Report, Types of Issues, Change Control Process, Baseline Management, Change Budget and Authority
PRINCE2 Practitioner - Issues Practice Example Questions
Test your knowledge of Issues Practice
Question 1
A project to implement a new customer relationship management system is in Stage 3. The Team Manager reports that a software module purchased from an external vendor is incompatible with the existing database architecture, requiring significant rework. The Project Manager needs to capture this situation formally. The vendor has confirmed they can provide a modified version in 4 weeks, but this will delay the planned integration testing. The Project Manager estimates the impact on the project schedule and budget before deciding on the next steps. Which statement best describes how the Project Manager should document this situation in the Issue Report?
Question 2
A construction project is entering its final stage when the Project Manager discovers that three separate issues logged in the Issue Register over the past two months are actually symptoms of a single underlying problem: insufficient foundation specifications provided by the original design team. Issue #47 concerns delays in concrete pouring, Issue #52 addresses unexpected ground settlement, and Issue #58 relates to structural engineer concerns about load-bearing capacity. All three issues remain open with different team members assigned to investigate them separately. What should the Project Manager do to optimize the management of these issues?
Question 3
What is the primary distinction between the change budget and change authority in project change control?