Managing a Stage Boundary Process

Apply stage transition and exception planning activities.

Covers planning the next stage, updating the project plan, updating the business case, reporting stage end, and producing exception plans when needed. Focuses on providing the Project Board with information for stage authorization decisions, reviewing lessons, and handling exceptions appropriately.
5 minutes 5 Questions

In PRINCE2 7, the Managing a Stage Boundary (SB) process is the critical 'gate' mechanism that enables the Project Board to maintain control over the project by reviewing progress and approving the next steps. It occurs towards the end of every management stage, except the final one. The primary ob…

Concepts covered: Report Stage End, Produce Exception Plan, Plan Next Stage, Update Project Plan, Update Business Case, Stage Transition Decisions

Test mode:
PRINCE2 Practitioner - Managing a Stage Boundary Process Example Questions

Test your knowledge of Managing a Stage Boundary Process

Question 1

A construction project is currently in Stage 2, which involves foundation work and initial structural development. During a quality review, the Project Manager discovers that unexpected ground conditions have been encountered, requiring additional geo-technical work. The Project Support has documented that this will add 15 days to Stage 2 and increase costs by £45,000. The Stage Plan shows the stage was due to complete in 12 days, and the Project Plan shows a tolerance of +10 days and +£30,000 for the overall project. Three other stages remain after this one. The Project Manager has prepared an Exception Report. Before finalizing updates to the Project Plan, what should the Project Manager ensure is addressed as the primary consideration?

Question 2

What is the primary purpose of the Exception Assessment conducted by the Project Board when a stage is forecast to exceed its tolerances?

Question 3

A telecommunications infrastructure project has just completed Stage 3, which delivered the network backbone installation across 12 regional sites. The End Stage Report shows the stage completed 2 weeks late (tolerance was +1 week) due to unexpected ground conditions at 3 sites, requiring additional engineering work costing £34,000 beyond the stage budget tolerance of +£20,000. The Project Manager escalated both time and cost exceptions during the stage, and the Project Board approved additional time and budget via Exception Plans. All technical specifications were achieved, and quality audits confirmed full compliance with industry standards. The Stage 4 Plan focuses on customer premise equipment installation and requires vendor equipment that has a 16-week lead time. The procurement process hasn't started yet because it was planned to begin after Stage 3 authorization. The Executive is concerned about mounting delays affecting the contracted go-live date with major business customers. What should the End Stage Report emphasize as the PRIMARY concern for Project Board consideration when deciding on Stage 4 authorization?

More Managing a Stage Boundary Process questions
136 questions (total)