Managing Product Delivery Process

Apply Team Manager activities for work package delivery.

Covers the Team Manager's activities: accept work package, execute work package, and deliver work package. Focuses on the interface between Project Manager and Team Manager, quality compliance during delivery, checkpoint reporting, and analyzing whether delivery approaches are effective for the project context.
5 minutes 5 Questions

In the context of PRINCE2 7, the Managing Product Delivery (MP) process serves as the defined interface between the management layer (Project Manager) and the delivery layer (Team Manager). Its primary objective is to ensure that the project's products are created, quality-checked, and approved wit…

Concepts covered: Accept Work Package, Execute Work Package, Deliver Work Package, Team Manager Responsibilities, Quality Compliance in Delivery

Test mode:
PRINCE2 Practitioner - Managing Product Delivery Process Example Questions

Test your knowledge of Managing Product Delivery Process

Question 1

A maritime logistics company is executing a Work Package to implement cargo tracking systems across 14 container shipping vessels. The Team Manager received authorization for 42 days with £156,000 budget and tolerances of +7 days and +£15,000. On day 31, the team has installed tracking systems on 10 vessels, spent £118,000, and forecasts completion in 41 days within all tolerances. During a checkpoint assessment, the Team Manager observes that installation crews have been mounting GPS antenna units at different locations on each vessel—some mount them on the forward mast, others on the bridge roof, and some on the stern superstructure. All mounting positions comply with the Product Description's requirement that 'GPS antennas must achieve unobstructed sky visibility with signal strength above -130dBm while maintaining secure attachment to vessel structure.' Each installation has passed signal quality testing and maritime safety inspections, with all systems providing accurate position data within the specified ±5 meter accuracy requirement. The shipping line's technical superintendent has inspected completed vessels and certified the installations as compliant with international maritime regulations. However, the varied antenna positions are resulting in different cable routing configurations and maintenance access procedures across the fleet, though all meet the documented functional and safety requirements. The Product Description specifies signal performance criteria and structural safety standards but does not mandate uniform antenna placement across all vessels. The Team Manager has been submitting regular checkpoint reports showing progress within tolerances, and the Project Manager has acknowledged these reports with approval for continuation. What should the Team Manager do in this situation?

Question 2

You are the Team Manager for a data analytics work package developing customer segmentation models for a marketing campaign. Your team of three data scientists has been working for four weeks and is at 65% completion within all tolerances. During this morning's code review session, you discover that your team has been accessing a supplementary customer dataset from the data warehouse that was not explicitly listed in the Work Package documentation. Your team lead explains they found this additional dataset three weeks ago and determined it significantly improves model accuracy by 18%, taking the precision from 76% to 94%. The dataset comes from the same secure data warehouse mentioned in the Work Package, contains similar customer attributes, and your team has followed all data governance protocols for access and handling. However, the Work Package specifically listed five source tables to be used, and this sixth dataset was not among them. The enhanced models have already been presented internally to your team's data quality reviewer, who praised the improved results. Your next Checkpoint Report to the Project Manager is tomorrow morning. What should have been your approach when your team first identified this additional dataset opportunity three weeks ago?

Question 3

Which document does a Team Manager use to report progress, issues, and forecast completion status to the Project Manager at regular intervals?