Plans Practice

Apply product-based planning and manage project plans effectively.

Covers project, stage, team, and exception plans, along with project product descriptions and work package descriptions. Focuses on the product-based planning technique, planning horizons, project stages, scope management, dependencies, and using tolerances to manage constraints. Includes delivery sustainability considerations and analyzing whether planning approaches are effective.
5 minutes 5 Questions

In PRINCE2 7, the Plans practice serves as the backbone for communication and control, defining how, when, and by whom the project's products will be delivered. It operates on the principle that planning is iterative, evolving from high-level outlines to detailed schedules as information becomes av…

Concepts covered: Project Plan, Stage Plan, Team Plan, Exception Plan, Project Product Description, Work Package Description, Product-based Planning Technique, Planning Horizon and Stages, Tolerances and Constraints

Test mode:
PRINCE2 Practitioner - Plans Practice Example Questions

Test your knowledge of Plans Practice

Question 1

A renewable energy project is implementing wind turbine installations across multiple coastal sites. The Project Manager developed a Project Plan during initiation that estimated 24 months duration, £45 million budget, and outlined six stages covering site preparation, turbine delivery, installation, grid connection, testing, and handover. Now, three months into the project, the Executive asks the Project Manager to present the Project Plan at a strategic investment committee meeting alongside four other organizational initiatives. The committee needs to compare projects and make portfolio-level resource allocation decisions for the upcoming fiscal year. The Project Manager notices that Stage 2 has experienced weather delays and cost overruns, and is considering whether to update the Project Plan with detailed variance analysis from Stage 2 before the committee meeting. The Project Manager also considers whether to include detailed risk registers, quality records, and lessons from Stage 1 to provide comprehensive context. The Executive emphasizes that the committee meeting will focus on strategic alignment, major milestone tracking, and overall viability assessment across the portfolio. How should the Project Manager prepare the Project Plan for this strategic committee presentation?

Question 2

A telecommunications company is upgrading its network infrastructure across 12 regional offices. The Project Manager conducted workshops where technical teams identified hardware components (routers, switches, fiber optic cables), configuration files, and network diagrams. The Operations team mentioned training materials and cutover plans. The Compliance Officer stated that security audit reports and data protection certifications must be obtained. When creating Product Descriptions, the Project Manager notices that 'Government Telecommunications License Renewal' is required for three regions where existing licenses expire during the project timeline. The Project Board asks how this license renewal should be handled in the product-based planning documentation, as it affects project delivery but involves external regulatory processes. How should the telecommunications license renewal be treated in the product-based planning approach?

Question 3

A construction project is implementing a new quality control system across multiple buildings. The Project Manager has assigned a Work Package to the Quality Team Manager for installing and testing air quality monitoring equipment in Building C. After two weeks, the Team Manager reports that the sensors specified in the Work Package are incompatible with Building C's ventilation system, which has older infrastructure than originally assessed. The Team Manager proposes using alternative sensors that meet the quality criteria but cost 15% more and require different calibration procedures. The Project Manager must decide how to proceed. What action should the Project Manager take regarding this Work Package situation?

More Plans Practice questions
285 questions (total)