Scrum Increments
The Incrment in Scrum refers to the sum of all the Product Backlog items completed during a Sprint and the value of the increments of all previous Sprints. The increment is a step toward a vision or goal. The increment should be in usable condition regardless of whether the Product Owner decides to release it. It must be 'Done', which means it must be in usable condition and meet the Scrum Team’s definition of 'Done'. An increment is a body of inspectable, done work that supports empirical transparency.
Guide to Scrum Increments
Why it is important:
Increments ensure that a usable version of working product is always available. Whether it needs to be released to stakeholders or not is a business decision. It enables empirical inspection and adaption, vital for Scrum's success.
What it is:
It is the total of all the 'Done' items from the Product Backlog carried out during a Sprint and the previous ones. This is the least that can be deployed or developed on further.
How it works:
An Increment is created each Sprint from the set of Product Backlog Items that were completed during this period. It adds to all previously done Increments.
Exam Tips: Answering Questions on Scrum Increments:
1. Define Scrum Increments correctly.
2. Memorize the Scrum Guide’s definition of 'Done'.
3. Understand how and why Increments play a crucial role in Scrum.
4. Know who decides whether to release an Increment.
5. Get comfortable with the nature of an Increment, i.e., it should always be in usable conditions.Remember, Scrum Increments can be released at any time during the project, not just at the end, and may not necessarily have to be released, but should be ready.
Study and understand these facts, concepts and processes until you are comfortable enough to apply them in an examination scenario. Good luck!
CSM - Scrum Increments Example Questions
Test your knowledge of Scrum Increments
Question 1
The Product Owner adds additional items to an increment in the middle of a Sprint. How should the Scrum Master respond?
Question 2
The product owner wants to add some new features in the middle of the sprint, what should be the Scrum Master’s response?
Question 3
How often should a potentially releasable increment be available?