Burndown Charts
Burndown Charts provide a graphical representation of work left to do versus time. The chart is updated daily and provides a simple view of the project's progress and projections. It can consistently communicate the team's status to stakeholders and within the team. Burndown Charts are effective tools for predicting when the work will be completed based on the remaining work and the team’s throughput. They also help uncover issues that are impeding the team’s progress.
Guide: Understanding and Answering Questions on Burndown Charts
Why it is important: Burndown Charts help in predicting the project completion date reliably. They are a measure of productivity and performance that enables the team to inspect and adapt their working strategies.
What it is: A Burndown Chart depicts the amount of work remaining (on the y-axis) over time (on the x-axis). The line (or the 'burn down') in the chart shows the pace at which the work is being completed.
How it works: At the start of a sprint, the total sprint work is at its peak. As tasks are completed, the line slopes downwards, indicating the progress. The steeper the line gets, the faster the team is completing tasks.
Exam Tips: Answering Questions on Burndown Charts
- Understand how to interpret the chart. A flat line indicates no work is done while a steeping line indicates more work is done.
- Use the chart to predict future trends, i.e., if the team continues at the current velocity, when the project will be finished.
- Be clear that Burndown Charts show both the progress of work and the remaining work.
- Understand that fluctuations in the Burndown Chart can be due to added, removed, or underestimated tasks.
- Know that in an ideal scenario, the line should reach zero at the end of the sprint. If it doesn’t, it means there's remaining work.
PMI-ACP - Burndown Charts Example Questions
Test your knowledge of Burndown Charts
Question 1
Your team's Burndown Chart displays a horizontal trend with a sudden drop in the end. How might you interpret this pattern?
Question 2
The Burndown Chart depicts oscillations above and below the ideal trend line. What could explain such a pattern?
Question 3
Halfway through the sprint, your team's Burndown Chart is showing an uptrend despite no new work being added. The team provides daily updates on work completed. What could be a plausible explanation?