Earned Value Management

Measurement of project performance

Earned Value Management (EVM) is a technique used for measuring project performance and progress in an objective manner. It combines scope, cost, and schedule measurements to assess project performance and progress.
5 minutes 5 Questions

Earned Value Management (EVM) is a methodology used in project management to measure project performance and progress in an objective manner. It integrates scope, schedule, and cost measurements to provide accurate forecasts of project performance issues.<br><br>EVM uses three key metrics: Planned …

Concepts covered: Estimate at Completion (EAC), Actual Cost (AC), Cost Performance Index (CPI), Cost Variance (CV), Planned Value (PV), Schedule Variance (SV), Estimate to Complete (ETC), Earned Value (EV), Schedule Performance Index (SPI), To-Complete Performance Index (TCPI)

Test mode:
CAPM - Earned Value Management Example Questions

Test your knowledge of Earned Value Management

Question 1

In a project that you are supervising, after 5 months you have spent $30,000 out of an allocated $50,000. What does the $30,000 represent?

Question 2

You are managing a project that was assigned a budget of $500,000. After 5 months into the project, you calculate that you have already spent $320,000. What is this amount referred to?

Question 3

You are in charge of the construction of a new building. You had planned for $750,000 for the first phase, but you have spent $950,000 at the end of the phase. What do we refer to this $950,000 as?

More Earned Value Management questions
107 questions (total)