Earned Value Management (EVM) is a technique used for measuring project performance and progress in an objective manner. It combines scope, cost, and schedule measurements to assess project performance and progress.
5 minutes
5 Questions
Earned Value Management (EVM) is a methodology used in project management to measure project performance and progress in an objective manner. It integrates scope, schedule, and cost measurements to provide accurate forecasts of project performance issues.<br><br>EVM uses three key metrics: Planned Value (PV), which represents the budgeted cost for work scheduled; Earned Value (EV), the budgeted cost for work completed; and Actual Cost (AC), the actual cost incurred for work completed.<br><br>From these primary metrics, project managers calculate performance indices:<br>- Cost Performance Index (CPI) = EV/AC, showing cost efficiency<br>- Schedule Performance Index (SPI) = EV/PV, indicating schedule efficiency<br><br>When CPI or SPI equals 1.0, performance is on target. Values greater than 1.0 indicate better-than-planned performance, while values less than 1.0 signal underperformance.<br><br>EVM also helps forecast final project costs through the Estimate at Completion (EAC) formula, which can be calculated various ways depending on future cost performance assumptions.<br><br>Additional important metrics include:<br>- Cost Variance (CV) = EV - AC<br>- Schedule Variance (SV) = EV - PV<br>- Variance at Completion (VAC) = BAC - EAC<br>- To Complete Performance Index (TCPI)<br><br>For CAPM certification, understand that EVM requires:<br>1. A well-defined scope with Work Breakdown Structure<br>2. A realistic schedule<br>3. A detailed budget linked to the schedule<br>4. A system to collect actual costs<br><br>EVM provides early warning signs of performance problems, allowing project managers to take corrective action. It transforms subjective assessments into objective measurements, making it a powerful tool in the CAPM professional's arsenal for project control and reporting.Earned Value Management (EVM) is a methodology used in project management to measure project performance and progress in an objective manner. It integrates scope, schedule, and cost measurements to provide accurate forecasts of project performance issues.<br><br>EVM uses three key metrics: Planned β¦
In a project that you are supervising, after 5 months you have spent $30,000 out of an allocated $50,000. What does the $30,000 represent?
Question 2
You are managing a project that was assigned a budget of $500,000. After 5 months into the project, you calculate that you have already spent $320,000. What is this amount referred to?
Question 3
You are in charge of the construction of a new building. You had planned for $750,000 for the first phase, but you have spent $950,000 at the end of the phase. What do we refer to this $950,000 as?
π Unlock Premium Access
Certified Associate in Project Management + ALL Certifications
π Access to ALL Certifications: Study for any certification on our platform with one subscription
Earn 15 PDUs needed for your CAPM certification
4454 Superior-grade Certified Associate in Project Management practice questions
Unlimited practice tests across all certifications
Detailed explanations for every question
CAPM: 5 full exams plus all other certification exams
100% Satisfaction Guaranteed: Full refund if unsatisfied
Risk-Free: 7-day free trial with all premium features!