Critical Path Method (CPM)
Identifying the longest path and earliest completion time in a schedule.
Critical Path Method (CPM) is a mathematical algorithm used for project scheduling that analyzes and represents the project network to identify the longest path through the network diagram, determining the shortest possible project duration. The critical path consists of activities that must be com…
Concepts covered: Schedule Network Diagram Construction, Float Calculation, Total Float and Free Float, Resource Leveling and Its Impact on the Critical Path, Forward and Backward Pass, Schedule Compression Techniques: Crashing and Fast-Tracking, Leads and Lags in Critical Path Method, Dependency Determination and Types in CPM, Lead and Lag Times and Their Effect on the Critical Path, Schedule Risk Analysis and Contingency Planning in CPM, Leads and Lags in Project Scheduling, PERT Analysis within CPM, Forward Pass and Backward Pass Calculations, Critical Path Identification, Working Calendars and Their Impact on CPM Scheduling, Dependency Determination and Types in CPM Scheduling, Critical Path, Activity Sequencing and Dependencies in CPM
PMI-SP - Critical Path Method (CPM) Example Questions
Test your knowledge of Critical Path Method (CPM)
Question 1
When performing both Forward Pass and Backward Pass calculations in a PDM network, what is the correct relationship between Early Start (ES), Early Finish (EF), Late Start (LS), and Late Finish (LF) for any activity on the critical path?
Question 2
In a forward pass calculation, Activity A has an ES of 8 days and duration of 6 days, while Activity B has an ES of 12 days and duration of 4 days. If these activities merge into Activity C, which scheduling principle best describes how to determine Activity C's Early Start (ES)?
Question 3
During network calculations, if Activity P's Early Finish (EF) is 30, Late Start (LS) is 25, and Total Float (TF) is 8 days, which formula would correctly determine its Free Float (FF)?