Controlling a Stage Process

Apply day-to-day stage control and management activities.

Covers the Project Manager's activities: authorize work packages, review work package status, receive completed work packages, review stage status, report highlights, capture and examine issues, escalate issues and risks, and take corrective action. Focuses on effective stage control, appropriate tailoring, and maintaining project momentum.
5 minutes 5 Questions

In the context of PRINCE2 7, the Controlling a Stage process represents the core of the Project Manager's day-to-day responsibilities during the project lifecycle. Its primary purpose is to assign work to be done, monitor such work, deal with issues, report progress to the Project Board, and take c…

Concepts covered: Receive Completed Work Packages, Authorize Work Package, Review Work Package Status, Review Stage Status, Report Highlights, Capture and Examine Issues, Escalate Issues and Risks, Take Corrective Action

Test mode:
PRINCE2 Practitioner - Controlling a Stage Process Example Questions

Test your knowledge of Controlling a Stage Process

Question 1

A financial services project is implementing a new customer portal. During week 12 of the 20-week project, the Marketing Director sends an email to the Project Manager stating that the company's rebranding initiative, announced two days ago, means the portal's color scheme and logo must change to align with the new corporate identity. The Marketing Director mentions this is 'just a cosmetic change' and requests it be completed within the current timeline. The Project Manager knows the design elements are embedded throughout the portal's user interface components, and the development team is currently focused on integrating the payment gateway module. The Project Board has not yet been informed of the rebranding initiative. What should the Project Manager do to properly handle this situation?

Question 2

A digital transformation project for a financial services company is entering its fourth month. The Project Manager needs to prepare a Highlight Report for the Project Board meeting scheduled for next week. The project has three concurrent workstreams: customer portal development (currently in stage 3), legacy system migration (in stage 2), and staff training (in stage 2). The customer portal workstream has experienced a two-week delay due to unexpected regulatory requirements, consuming an additional £45,000 from tolerance. The legacy system migration discovered data quality issues requiring remediation, but this was managed within Work Package tolerances. Staff training is progressing as planned. The Project Board has previously expressed concern about regulatory compliance and budget consumption. What should the Project Manager emphasize in the Report Highlights section to provide the most value to the Project Board?

Question 3

What is the primary purpose of the Authorize Work Package activity?

More Controlling a Stage Process questions
327 questions (total)