Claims Avoidance and Early Claim Management

5 minutes 5 Questions

In the Certified Construction Manager (CCM) framework, Claims Avoidance and Early Claim Management are core risk management practices aimed at preventing disputes from escalating into costly, time-consuming claims or litigation. Claims Avoidance begins before construction starts. The Construction Manager (CM) works to reduce the root causes of claims, which typically include ambiguous contract language, incomplete or conflicting design documents, unrealistic schedules, differing site conditions, inadequate owner decision-making, and poor communication. Key avoidance strategies include thorough constructability and biddability reviews, clear and fair risk allocation in the contract documents, realistic baseline schedules, defined change-order and notice procedures, partnering sessions to align stakeholder expectations, and robust documentation protocols such as daily reports, meeting minutes, RFIs, and photographic records. By establishing these systems early, the CM creates a transparent project environment where issues are surfaced and resolved rather than hidden. Early Claim Management addresses what happens once a potential issue arises. The CM's role is to recognize the warning signs promptly—such as unresolved RFIs, delayed approvals, or contractor notices of delay—and to act quickly to contain them. This involves verifying timely written notice per contract requirements, conducting a prompt and objective evaluation of entitlement (is the contractor owed time or money?) and quantum (how much?), maintaining contemporaneous records of impacts, and encouraging resolution at the lowest possible level through negotiation. Alternative dispute resolution tools, including Dispute Review Boards, mediation, and step negotiation, are preferred over arbitration or litigation. The CM must remain impartial, protecting the owner's interests while treating the contractor fairly, since credibility is essential to settlement. Together, these practices preserve budget, schedule, and relationships. Unmanaged claims erode trust, drain resources, and can derail a project, whereas proactive avoidance and early intervention convert potential disputes into manageable change orders or mutually acceptable settlements, reflecting the CCM standard of professional risk stewardship.

Claims Avoidance and Early Claim Management (CMAA CCM – Risk Management)

Why This Topic Matters
Claims are among the most expensive, time-consuming, and relationship-damaging events that can occur on a construction project. For the Certified Construction Manager (CCM) candidate, the Risk Management domain tests your ability to prevent claims before they arise and to manage them quickly and professionally when they do. CMAA's Construction Management Standards of Practice (CMSOP) treats claims avoidance as a core responsibility of the CM throughout every project phase, not merely as a reactive legal exercise after a dispute surfaces. An unresolved claim can erode the owner's budget, delay completion, trigger litigation, and destroy the collaborative atmosphere that successful project delivery depends on. Understanding how claims originate, how they are prevented, and how they are resolved early is therefore central to both the exam and real-world practice.

What Is a Claim?
In construction management terminology, it is critical to distinguish three related concepts:
• A change is a modification to the scope, time, or cost of the contract that both parties agree to and formalize through a change order.
• A claim is a demand or assertion by one party seeking additional time, money, or other relief under the contract when the parties have not yet agreed that the party is entitled to it. A claim typically arises when a requested change is denied, disputed, or left unresolved.
• A dispute is a claim that has been formally rejected or remains unresolved after negotiation and is escalated into the contract's dispute resolution process.
Put simply: an unresolved change request becomes a claim; an unresolved claim becomes a dispute. The CM's goal is to keep issues at the change level and resolve them promptly so they never mature into claims or disputes.

Common Root Causes of Construction Claims
Exam questions frequently ask you to identify the underlying cause of a claim. The most common categories are:
• Differing site conditions – subsurface or latent physical conditions that differ materially from those indicated in the contract (Type I) or from conditions ordinarily encountered (Type II).
• Defective or ambiguous plans and specifications – errors, omissions, and conflicts in design documents, often implicating the owner's implied warranty of design adequacy (the Spearin doctrine).
• Scope changes and owner-directed changes – additions, deletions, or substitutions that were not properly priced or documented.
• Delays and disruptions – late owner decisions, late access, late delivery of owner-furnished items, permitting problems, or interference by other contractors.
• Acceleration – directed or constructive demands to finish earlier than the adjusted schedule requires.
• Weather and force majeure events – generally excusable but non-compensable unless the contract provides otherwise.
• Payment problems – late payments, improper withholding, or retainage disputes.
• Poor communication and unclear roles – slow RFI responses, unclear authority, and inconsistent direction.
• Unrealistic schedules or budgets established before the project began.

Claims Avoidance: How It Works
Claims avoidance is proactive and begins long before construction. CMAA emphasizes that the CM has opportunities in every phase to reduce claim exposure.

Pre-Design and Design Phase
• Develop a comprehensive Risk Management Plan that identifies, analyzes, allocates, and tracks project risks.
• Perform constructability reviews to catch errors, omissions, coordination conflicts, and unbuildable details before bidding.
• Conduct thorough site investigations and share geotechnical data with bidders to reduce differing site condition claims.
• Draft clear, complete, and coordinated contract documents with unambiguous language, well-defined scope, and consistent terms.
• Allocate risk to the party best able to control or bear it; unreasonable risk-shifting to the contractor tends to inflate bids and breed claims.
• Build realistic schedules and budgets with appropriate contingencies.
• Include fair and workable contract clauses: changes, differing site conditions, time extensions, notice requirements, and a tiered dispute resolution procedure.

Procurement Phase
• Prequalify bidders to ensure competence and financial capacity.
• Hold a thorough pre-bid conference and answer questions through formal written addenda.
• Review bids for unbalanced pricing or mistakes that foreshadow later claims.

Construction Phase
• Hold a pre-construction conference to set expectations on communication protocols, submittal and RFI turnaround, change order procedures, and documentation.
• Consider partnering or team alignment sessions to build trust and establish an issue-escalation ladder.
• Respond to RFIs and submittals promptly; delayed responses are a leading cause of delay claims.
• Maintain disciplined schedule management: review baseline and updated CPM schedules, track float, and identify delays as they occur.
• Enforce a timely and fair change order process so that potential changes are priced and negotiated quickly.
• Keep complete, contemporaneous documentation: daily reports, photographs, meeting minutes, correspondence logs, RFI and submittal logs, and schedule updates. Good records are the single most important tool in both avoiding and resolving claims.
• Process payments on time and handle retainage per the contract.
• Communicate openly and consistently with all parties.

Early Claim Management: How It Works
Even with excellent avoidance practices, some claims will occur. The CM's objective is to recognize them early and resolve them at the lowest possible level, as quickly and inexpensively as possible. A typical early claim management sequence is:

1. Recognition and notice. Identify potential claim events immediately. Nearly all contracts contain notice provisions requiring the contractor to notify the owner within a specified number of days of discovering a changed condition or delay. The CM should track these requirements and ensure the owner responds appropriately. Failure to give timely notice can be grounds to deny a claim, but the CM should focus on resolving merit rather than relying purely on technicalities.
2. Documentation and investigation. Gather and preserve all relevant records, inspect the condition, photograph it, and interview field personnel while memories are fresh.
3. Evaluation of entitlement. Determine whether the contract supports the claim: Is the event covered by a changes clause, differing site conditions clause, or time extension clause? Was proper notice given? Is the delay excusable, and if so, compensable?
4. Evaluation of quantum. Analyze the cost and time impact. Use the schedule (time impact analysis or similar forensic method) to establish critical-path delay. Verify labor, material, equipment, and overhead costs against records.
5. Negotiation. Meet with the contractor promptly, exchange information, and attempt to reach a fair settlement, converting the claim into a change order where appropriate.
6. Escalation through the dispute resolution ladder. If negotiation fails, follow the contract's stepped process, typically: field-level negotiation, executive-level negotiation, mediation, Dispute Review Board (DRB) or Dispute Resolution Board, arbitration, and finally litigation. Each step up the ladder increases cost, time, and loss of control over the outcome, so early resolution is always preferred.

Delay Classification (Frequently Tested)
• Excusable and compensable – caused by the owner or its agents; contractor gets time and money.
• Excusable and non-compensable – caused by neither party (e.g., unusually severe weather); contractor gets time only.
• Non-excusable – caused by the contractor; no time, no money, and possibly liquidated damages.
• Concurrent delay – both parties cause delay simultaneously; typically time is granted but costs are not recovered by either party.

The CM's Role and Posture
In an agency CM arrangement, the CM acts as the owner's advisor and must evaluate claims objectively, fairly, and in good faith, protecting the owner's interests while treating the contractor equitably. The CM should never ignore a legitimate claim or delay a decision in hopes it goes away; unresolved issues grow more expensive over time. In an at-risk CM arrangement, the CM holds the trade contracts and must manage subcontractor claims directly while also presenting its own claims to the owner, requiring careful attention to flow-down clauses and pass-through claims.

Exam Tips: Answering Questions on Claims Avoidance and Early Claim Management
• Always favor the proactive, early, lowest-level answer. If an option involves preventing an issue, documenting it immediately, or negotiating at the field level, it is usually correct over options that escalate to arbitration or litigation.
• Remember the hierarchy: change → claim → dispute. Questions may test whether you can distinguish an agreed change order from a contested claim from a formally escalated dispute.
• Know the dispute resolution ladder in order: negotiation, mediation, DRB, arbitration, litigation. Mediation is non-binding and facilitated; arbitration is typically binding and adjudicative; litigation is the most costly and least controllable.
• Documentation is almost always the right answer when a question asks what is most important for avoiding or defending claims. Contemporaneous records beat after-the-fact reconstruction every time.
• Notice provisions matter. If a question describes a contractor discovering a differing site condition, the first required step is written notice per the contract before disturbing the condition.
• Think in phases. The exam may ask when a specific avoidance tool is used: constructability reviews occur in design; pre-bid conferences in procurement; pre-construction conferences and partnering at the start of construction.
• Classify delays correctly. Match the cause to the outcome: owner-caused equals time and money; neither-party-caused equals time only; contractor-caused equals neither.
• Watch for the Spearin doctrine in questions about defective plans and specifications: the owner implicitly warrants that the design is adequate, so design errors generally entitle the contractor to relief.
• Reject unethical or adversarial options. Answers suggesting the CM should ignore notices, stall payments, or exploit technicalities to defeat a meritorious claim are wrong under CMAA's professional standards.
• Read for the CM's role. Determine whether the scenario is agency CM or CM-at-risk; the correct action may differ based on who holds the trade contracts and bears the risk.
• Eliminate extremes. Options that are absolute (never, always, immediately terminate) or that skip steps in the contractual process are rarely correct.
• Tie everything back to the Risk Management Plan. Claims avoidance is a subset of risk management; when in doubt, choose the answer that identifies, allocates, and monitors risk systematically.

Summary
Claims avoidance and early claim management is about preventing conflict through clear contracts, sound planning, open communication, and rigorous documentation, and then, when issues do arise, recognizing them promptly, giving proper notice, evaluating entitlement and quantum objectively, and resolving them at the lowest and earliest step possible. Master the definitions, the root causes, the phase-by-phase avoidance tools, the delay classifications, and the dispute resolution ladder, and you will be well prepared for this portion of the CCM examination.
Test mode:

CMAA CCM - Claims Avoidance and Early Claim Management Example Questions

Test your knowledge of Claims Avoidance and Early Claim Management

Question 1

On an airport terminal expansion, the contractor submits a request for equitable adjustment for lost productivity. It states that the owner kept two gates in service for six weeks past the dates in the contract phasing plan. The contractor gave timely written notice, and the owner wants to settle early if the request has merit. What should the construction manager do NEXT?

Question 2

On a county jail, the contractor submits a time impact analysis requesting 20 working days and extended general conditions for late owner approval of detention hardware shop drawings. The construction manager's review of the monthly schedule updates shows that during the same 20 days, the contractor's precast cell modules arrived late from its own supplier. That activity was also on the critical path. What should the construction manager recommend to the owner?

Question 3

On a fire station, an owner-directed change to the apparatus bay adds work on the critical path. The contractor gives timely written notice and submits a fragnet requesting 15 working days. The owner wants to keep the opening date and tells the construction manager to have the contractor hold the original completion date while the request remains pending. The contractor then adds a second shift and states that it is working under protest. What should the construction manager recommend to best limit the owner's claim exposure?

More Claims Avoidance and Early Claim Management questions
22 questions (total)