Risk Management

Continuous risk management from conception to post-occupancy: the risk management plan, risk breakdown structure, identification, qualitative and quantitative analysis, threats and opportunities, the risk register, risk allocation, insurance, claims avoidance and dispute resolution.

5 minutes 5 Questions

Risk Management, in the context of the Certified Construction Manager (CCM) credential and the CMAA (Construction Management Association of America) body of knowledge, is the systematic process of identifying, analyzing, responding to, and monitoring risks that could affect a construction project's…

Test mode:

CMAA CCM - Risk Management Example Questions

Test your knowledge of Risk Management

Question 1

On a fire station, the owner set contingency at the P80 value from a Monte Carlo cost model run at design completion. Midway through construction, foundations and underground utilities are complete. This retires the two largest risks on the tornado diagram, and $40,000 of contingency has been spent. The owner asks whether the remaining contingency balance is still the right amount. What should the construction manager do to answer this question?

Question 2

How does partnering differ from mediation, arbitration and dispute review boards as a risk management tool on construction projects?

Question 3

During design of a wastewater pump station, the owner asks the construction manager to write the analysis methodology section of the risk management plan. The owner wants a probabilistic cost and schedule simulation run on every identified risk. The project is modest in size, historical data for many risks is thin, and the risk workshop budget is limited. Which approach should the construction manager write into the plan?