Partnering
Partnering, within the Certified Construction Manager (CCM) body of knowledge and Risk Management domain, is a structured, collaborative approach in which the owner, construction manager, designer, contractors, and key subcontractors commit to working as a unified team rather than as adversarial parties. It is typically formalized at project start through a facilitated partnering workshop that produces a partnering charter: a signed statement of shared goals (safety, schedule, budget, quality), communication protocols, and an issue-escalation ladder. From a risk management perspective, partnering is a proactive risk mitigation strategy. Construction risk often arises not only from technical uncertainty but from poor communication, misaligned incentives, and positional disputes. Partnering addresses these sources by establishing trust, encouraging early identification of problems, and promoting joint problem-solving before issues mature into claims. The escalation ladder requires that disputes be resolved at the lowest possible level within defined timeframes, moving upward only if unresolved, which reduces delay and litigation exposure. Key elements the CCM should understand include: executive-level commitment from all organizations; regular partnering follow-up sessions to measure team performance against charter goals; open-book communication and information sharing; and alignment with contractual dispute-resolution provisions such as mediation or dispute review boards. Partnering does not replace the contract; it operates alongside it, and the charter is generally non-binding. Benefits documented by agencies such as the U.S. Army Corps of Engineers and state DOTs include fewer claims, reduced cost growth, improved schedule performance, better safety records, and higher owner satisfaction. Limitations include the time and cost of facilitation, dependence on genuine participation, and the risk of superficial 'checkbox' partnering if leadership is not sincere. For the CCM exam, remember that partnering is a relationship-based risk management tool emphasizing shared objectives, early issue resolution, and collaborative culture, directly supporting the CMAA Standards of Practice for Risk Management.
Partnering in Construction Risk Management: A Complete CCM Exam Guide
Construction projects bring together parties with different and often conflicting commercial interests: the owner wants maximum scope for minimum cost, the contractor wants to protect margin, and the designer wants to protect the design intent and limit liability. When these interests collide, the result is adversarial behavior, defensive paperwork, delayed decisions, claims, and litigation. Industry studies routinely show that disputes consume a significant percentage of total project cost and are one of the leading sources of schedule overruns.
Partnering is the construction industry's structured response to this problem. Within the CMAA Body of Knowledge and the Construction Management Standards of Practice, Partnering sits inside the Risk Management domain because it is fundamentally a dispute avoidance technique: it reduces the probability and severity of claims, protects the schedule and budget, and preserves working relationships. On the CCM exam, Partnering questions test whether you understand it as a proactive, relationship-based risk mitigation tool, not as a contract form, not as a legal remedy, and not as a dispute resolution method that kicks in after a conflict has already escalated.
What Partnering Is
Partnering is a voluntary, structured process in which the key stakeholders of a project (owner, construction manager, designer, general contractor, major subcontractors and suppliers, and sometimes regulators or end users) formally commit to work collaboratively toward shared project goals, communicate openly, and resolve issues at the lowest possible level as quickly as possible.
Key defining characteristics you must know:
1. It is not a contract. Partnering does not alter the legal rights, duties, or risk allocation set out in the contract documents. The contract still governs. Partnering changes behavior and process, not legal obligations.
2. It is voluntary. Although an owner may include a clause encouraging or requiring participation in partnering sessions, the commitments made in the partnering charter are moral and professional, not legally enforceable.
3. It is proactive. Partnering is established at the beginning of the project (ideally before or at the start of construction), before problems arise. Mediation, arbitration, and litigation are reactive; partnering is preventive.
4. It is based on mutual goals and trust. The parties identify objectives they all share (safety, quality, on-time completion, fair profit, no claims, good public relations) and agree on how they will treat each other.
5. It includes a defined issue-resolution process. Problems are solved at the field level first and escalated up a predefined ladder only if they cannot be resolved within an agreed time.
Two common forms appear in exam material:
- Project Partnering: a one-time arrangement established for a single project. This is the most common form in public work and the one most often tested.
- Strategic (Long-Term) Partnering: an ongoing relationship across multiple projects between an owner and selected firms, common in the private sector where repeat work is possible.
Do not confuse Partnering with Alliancing or Integrated Project Delivery (IPD), which do involve contractual risk and reward sharing. Partnering is a non-contractual overlay that can be applied to any delivery method: Design-Bid-Build, CM at-Risk, Design-Build, or agency CM.
How Partnering Works: The Process
Step 1: Owner Commitment and Decision to Partner
Partnering only succeeds when it is championed from the top. The owner (often on the recommendation of the Construction Manager) decides to use partnering, budgets for it, and signals that executive leadership supports it. Lack of genuine senior-level commitment is the most frequently cited reason partnering fails.
Step 2: Selecting a Neutral Facilitator
A trained, independent facilitator is engaged, with the cost typically shared among the parties or carried by the owner. The facilitator has no stake in the project outcome and is responsible for running workshops, drawing out concerns, and guiding the group to consensus. The CM may recommend the facilitator but should generally not be the facilitator, since the CM is a party to the project.
Step 3: The Initial Partnering Workshop (Kickoff)
Typically a one- to two-day session held early in the project, often off-site, attended by decision-makers from each organization. Activities include:
- Introductions and team building to break down organizational barriers
- Identifying each party's goals and concerns
- Developing shared project goals
- Agreeing on communication protocols
- Creating the issue resolution ladder
- Drafting and signing the Partnering Charter
Step 4: The Partnering Charter
The charter is a short, signed document that states the mission, the mutual goals, and the behavioral commitments of the team. All participants sign it, and it is often displayed prominently in the field office. Remember for the exam: the charter is a statement of intent and is not legally binding.
Step 5: The Issue Resolution Ladder (Escalation Process)
This is the operational heart of partnering. The team agrees that:
- Issues are first addressed by the people closest to the problem (e.g., superintendent and inspector).
- If unresolved within a set time (often 24 to 72 hours), the issue escalates to the next level (project managers), then to executives.
- Each level has a time limit so issues cannot stall.
- Escalation is not failure; it is the system working as designed.
- Ignoring an issue or going around the ladder is discouraged.
Step 6: Follow-Up and Continuous Evaluation
Partnering is not a one-day event. The team schedules periodic follow-up workshops (monthly or quarterly), issues partnering evaluation surveys or scorecards in which each party rates communication, cooperation, issue resolution, and progress toward goals, and adjusts the process when scores slip. New team members who join mid-project are oriented to the charter.
Step 7: Closeout and Lessons Learned
At project end the team evaluates what worked, documents lessons learned, and, in strategic partnering, carries improvements to the next project.
The Construction Manager's Role in Partnering
The CM is frequently the catalyst. Per CMAA practice, the CM:
- Advises the owner on whether partnering is appropriate and estimates its cost and benefit
- Helps draft any partnering language for the bid documents or contracts
- Assists in selecting the facilitator and organizing the workshop
- Ensures the issue resolution ladder is integrated with the project's change management, RFI, and claims procedures
- Monitors partnering health through surveys and reports status to the owner
- Models partnering behavior in daily field interactions
Benefits and Limitations
Benefits: fewer claims and disputes, faster decisions, improved safety and quality, reduced cost of administration and litigation, better morale, higher likelihood of on-time completion, and improved relationships for future work.
Limitations: requires upfront time and money; fails without real top-level commitment; cannot fix a fundamentally flawed contract or unrealistic budget and schedule; can be undermined by personnel turnover; may create a false sense of security if parties stop documenting properly. Partnering supplements, but never replaces, sound contract administration and documentation.
How to Answer Exam Questions on Partnering
CCM questions on this topic are usually scenario-based or definitional. Use this approach:
1. Identify the timing in the scenario. If the question describes activity at project start aimed at preventing problems, the answer is partnering. If a dispute has already crystallized and the parties need a third party to decide or help settle it, the answer is a dispute resolution method (negotiation, mediation, DRB, arbitration, litigation), not partnering.
2. Check whether the answer choice implies legal force. Any option that says partnering changes contract terms, shifts liability, waives claims, or is legally enforceable is wrong.
3. Look for the role of the owner. Options that identify owner commitment as critical to success are usually correct. Options suggesting partnering can succeed with only field-level buy-in are usually wrong.
4. Remember the neutral facilitator. If asked who should lead the workshop, the best answer is an independent facilitator, not the owner, CM, or contractor.
5. Know the issue resolution ladder. Questions often ask what should happen when field staff cannot agree: escalate to the next level within the agreed time frame, not file a claim, not stop work, not wait indefinitely.
6. Recognize partnering as ongoing. If an answer choice treats partnering as a single kickoff meeting with no follow-up, it is incomplete; the best answer will include periodic evaluation.
Exam Tips: Answering Questions on Partnering
- Tip 1: Classify it correctly. Partnering belongs to Risk Management and dispute avoidance. It is a risk mitigation strategy. If an answer set includes risk transfer, risk acceptance, risk avoidance, and risk mitigation, partnering aligns with mitigation.
- Tip 2: Memorize the three non-negotiables. Partnering is voluntary, non-contractual, and proactive. Eliminate any option contradicting these.
- Tip 3: Charter means commitment, not contract. When the exam mentions the partnering charter, the correct description is a signed statement of shared goals and values with no legal enforceability.
- Tip 4: Watch for distractors naming contractual collaboration. IPD, alliancing, and multi-party agreements share risk through contract; partnering does not. A question about shared risk-reward pools is not about partnering.
- Tip 5: The CM recommends and supports; the owner champions; the facilitator runs the workshop. Keep these three roles separate when choosing an answer.
- Tip 6: Lowest level, fastest time. Any question about where disputes should be resolved in a partnered project points to the lowest possible organizational level in the shortest reasonable time, with structured escalation.
- Tip 7: Cost is shared or owner-borne and is a small investment relative to avoided claims. Options claiming partnering has no cost or is paid solely by the contractor are suspect.
- Tip 8: Partnering does not eliminate documentation. If a scenario suggests the team stopped issuing written notices because they are partnering, recognize this as a mistake. Good partnering coexists with disciplined contract administration.
- Tip 9: Read for the word best. When multiple answers are plausible, choose the one that describes a complete, structured, facilitated, ongoing process with executive support, rather than an informal or one-time gesture.
- Tip 10: Connect to outcomes. Correct answers about the purpose of partnering reference reduced disputes and claims, improved communication, and achievement of mutual goals, not lower bid prices or elimination of the need for a CM.
Quick Review Summary
Partnering is a voluntary, non-contractual, facilitated process established at the start of a project in which stakeholders commit to shared goals, open communication, and a time-bound issue escalation ladder, documented in a signed but non-binding charter and sustained through periodic evaluation. It is the premier dispute avoidance tool in the Construction Manager's risk management toolkit, it depends on owner commitment and a neutral facilitator, and it supplements, never replaces, the contract and proper documentation. Master these points and you will handle any Partnering question on the CCM exam with confidence.
CMAA CCM - Partnering Example Questions
Test your knowledge of Partnering
Question 1
On a mixed-use housing development, the owner's project manager and the general contractor's project manager are both replaced six months into construction. Neither newcomer attended the initial partnering workshop. Since the change, two field issues have stalled past the charter's time limits and have not been elevated. As the construction manager, what is the BEST recommendation to the owner?
Question 2
The construction manager is drafting the issue resolution ladder for the partnering charter on a data center. The owner, CM, general contractor and the electrical and mechanical subcontractors will each staff field, project and executive roles. Commissioning milestones leave little float, so unresolved field questions could quickly turn into delay claims. Which ladder design best supports claims avoidance?
Question 3
On a water treatment plant, the owner and general contractor disagree over whether extended membrane startup testing is extra work. The disagreement has gone through every tier of the partnering issue resolution ladder, and the executives remain deadlocked after the charter's time limit. The contract provides that unresolved claims go to a standing dispute review board and then to binding arbitration. The contractor has filed its claim in writing as the contract requires. What should the construction manager do FIRST?